30-100
All construction, such as street grading, street paving, drainage
structures, curb and gutter, storm sewers, sanitary sewers, and water
mains, shall be subject to inspection during the construction period
by the proper authorities of the City, and shall be constructed in
accordance with the approved engineering plans, Subdivision Ordinance
requirements and the City of River Oaks Standard Specifications governing
such work.
30-101
Upon completion of construction the developer or subdivider
shall request the City Engineer to make a final inspection of the
work and to file a report of the results of such inspection.
(Ordinance 1209-2018 adopted 11/27/18)
31-100
All contractors employed by the Subdivider shall furnish the
City a good and sufficient performance bond, in an amount equal to
one hundred percent (100%) of the costs of the improvements required,
and a good and sufficient two (2) year maintenance bond, in an amount
equal to fifty percent (50%) of the costs of the improvements required;
both bonds shall be executed by a reputable and solvent corporate
surety, holding a license to do business in the State of Texas, or
other security approved by the City Attorney, in favor of the City
to indemnify the City against any performance for project completion
or repairs which may become necessary to any part of the construction
work performed in connection with the subdivision, arising from defective
workmanship or materials used therein, for a full period of two (2)
years from the date of final acceptance of the entire project. Final
acceptance will be withheld until said maintenance bond is furnished
to the City. Such Bond or other security shall be approved as to form
and legality by the City Attorney.
(Ordinance 1209-2018 adopted 11/27/18)
32-100
Acceptance of improvements by the City shall be in the form
of a letter from the City Manager or other authorized City Official
to the Subdivider stating that inspections were conducted as the facilities
were completed in accordance with specifications and standards provided
for herein or approved by the City Council at the time the final plat
was approved for said subdivision.
32-101 After
the work has been accepted by the City, as-built construction drawings
of such work shall be submitted to the City. One (1) full size set
of mylars and one (1) full size set of prints shall be submitted to
the City Engineer.
(Ordinance 1239-2019, sec. 49, adopted 8/13/19)
33-100
No building permit, water, sewer, plumbing or electrical permit
or service shall be issued or allowed to a Subdivider, owner or any
other person with respect to any property in any subdivision covered
by this Ordinance until such time as all of the applicable requirements
of this Ordinance have been satisfactorily completed and the construction
accepted by the City.
33-101 The
City Manager may authorize special exceptions to Article 33, subject
to appropriate conditions and safeguards, in order to permit reasonable
development and improvement of property.
(Ordinance 1209-2018 adopted 11/27/18; Ordinance 1239-2019, sec. 50, adopted 8/13/19)