The municipality may include all costs incurred in the review
fee charged to an applicant.
A. The review fee may include, but not be limited to, costs for the
following:
(1) Administrative/clerical processing;
(2) Review of the SWM site plan, agreements, covenants or restrictions
required by the chapter by the municipality, the Municipal Engineer
and other municipal consultants, including the Municipal Solicitor;
(3) Coordination and meetings with the applicant;
(4) The inspection of erosion and sediment control measures, BMPs, conveyances
and other related improvements during construction;
(5) Review of project communications, reports, and additional supporting
information;
(7) The final inspection upon completion of the BMPs, conveyances, and
other stormwater management facilities and related improvements presented
in the SWM site plan; and
(8) Review of final as-built plan submission and revised calculations,
and inspections as needed.
B. The applicant shall also reimburse all expenses incurred by the municipality
for any additional work or municipal consultant fees required to enforce
any permit provisions regulated by this chapter, correct violations,
and ensure proper completion of remedial actions.
C. Exempt
projects fee.
[Added 6-12-2023 by Ord. No. 2023-3]
(1) Applicants submitting projects that meet the requirements of §
188-14A are required to pay a fee of $1.00 per square foot of newly proposed impervious surface. Removal of any existing impervious areas shall not be considered in the calculation of this fee.
(2) Fee
may be amended from time to time by resolution of Borough Council.
(3) Fee
will be deposited into a designated stormwater fund managed by the
Borough specifically for improvements to Borough-owned stormwater
infrastructure and within the conveyance system.