[Amended 4-3-2023 by Ord.
No. 1284]
That certain document, one copy of which is on file in the office of the Building Official, being marked and designated as "
California Building Code," Volumes 1 and 2,
California Building Code (CBC) Chapter
1, Division I, Scope and Administration Section 1.8.3 and Division II Administration; and together with Appendices Chapter G - Flood-Resistant Construction, Chapter H - Signs, Chapter I - Patio Covers, Chapter J - Grading, Chapter K - Central Valley Flood Protection Plan, and Chapter P - Emergency Housing, and subsequent additions and editions thereto which said Code provides for the proper regulations for erecting, constructing, enlarging, altering, repairing, removing, conversions, demolition, occupancy, equipment, use height and maintenance of buildings or structure in the City and providing for the issuance of permits and collections of fees therefor and providing penalties for violation thereof, as hereinafter amended, deleted and added to, and the same is hereby adopted by reference as the Building Code of the City of Oakdale.
[Amended 4-3-2023 by Ord.
No. 1284]
The
California Building Code adopted in this article is hereby
modified by the following amendments, additions and deletions.
Section 1900.4.4 is added to read:
Concrete Slab Floors. Section 1900.4.4(a) Concrete Slab Floors,
when used as a finished floor or as a base for other floor finish
in buildings which will contain conditioned air space shall be constructed
according to the following additional requirements, or as approved
by the Building Official:
Vapor Barrier. Section 1900.4.4(a)1 A water proofing membrane,
ten mil, or water proofing acceptable to the Building Official shall
be placed on the compacted subgrade. The membrane shall extend to
the exterior walls and terminate at the exterior footings.
Sand Fill. Section 1900.4.4(a)2 One inch (1") of clean sand
shall be placed on the membrane before placement of concrete.
[Amended 4-3-2023 by Ord.
No. 1284]
Section 503.1 table is added to read:
Table 503.1
Basic Allowable Area in Square Feet for Determination of Fire
Sprinkler Installation.
|
---|
Occupancy Types
|
Square Footage
|
---|
Assembly Group A - A-1, A-2, A-3, A-4, A-5
|
5000
|
Business Group B
|
5000
|
Educational Group E
|
5000
|
Factory Group F - F-1, F-2,
|
5000
|
High-Hazard Group H - H-1, H-2, H-3, H-4, H-5
|
Not permitted without sprinklers.
|
Institutional Group I - I-1, I-2, I-3, I-4
|
Not permitted without sprinklers.
|
Mercantile Group M
|
5000
|
Residential Group R - R-1, R-2, R-3
|
Not permitted without sprinklers.
|
Storage Group S - S-1, S-2
|
5000
|
Utility and Miscellaneous Group U
|
5000
|
Any building of any type occupancy, which exceeds two stories
in height.
|
Any size.
|
Exception: Carports, sheds, tanks, towers, and
Agricultural buildings.
Area separation walls shall not be used for the purpose of eliminating
automatic fire sprinkler systems required by this section
See CBC/CFC for additional requirements.
Section 503.2 is added to read:
(a) The classification for occupancies shall be as set forth in Chapter
3 of the 2022 Edition of the
California Building Code.
(b) Table 503.1, attached to this ordinance and incorporated
herein by reference, shall be used to determine whether automatic
fire extinguishing systems shall be required for new construction,
additions to existing buildings, or any change in use of existing
buildings. (Table 503.1 may be found on file in the office of the
City Clerk.)
(c) The installation of Fire Walls may not be used to divide
new buildings into separate areas for the purpose of fire sprinkler
system elimination. In existing structures, constructed prior January
1, 2008, each area created by an area separation wall constructed
in accordance with the
California Building Code may be separately
measured to determine the applicability of automatic fire extinguishing
systems.
[Amended 4-3-2023 by Ord.
No. 1284]
"Appendix Chapter" "J" is adopted and amended to read:
Section J101.3 is added to read:
Add section 101.3: "Compliance with local law. All grading shall be done in accordance with Chapter
29 of the Oakdale Municipal Code."
Section J104.5 is added to read:
This site plan is subject to review by the Public Works Department.
Any site over one acre in size (including any area adjacent to site
that is used for grading and/or construction purposes) may be subject
to a NPDES Storm Water Discharge Permit. In these cases, a Storm Water
Pollution Prevention Plan (SWPPP) must be created in accordance with
the Caltrans Storm Water Pollution Prevention Plan Manual and submitted
for approval at least seven working days before any construction or
grading activity is to begin."
Section J105.3 is added to read:
"Storm water inspections. Grading sites are subject to inspection at any time by the Public Works Department staff to ensure compliance with Chapter
29 of the Oakdale Municipal Code."
Section J110.3 is added to read:
"Storm drain inlets that are down slope from the grading site
must be protected from sediment displaced by the grading activities.
Once grading is completed, sediment on streets and sidewalks that
has the potential to be washed into the storm drain system shall be
cleaned up before removing the protective barriers."
[Amended 4-3-2023 by Ord.
No. 1284]
That certain document in book form entitled "2022 California
Residential Code" including all the following appendices with the
exception of Appendix AL-Permit Fees, and subsequent additions and
editions thereto appendix Chapter "H" Patio Covers as published by
California Building Standards Commission. One copy of which is now
on file in the office of the Building Official of the City of Oakdale
is hereby adopted by reference as the California Residential Code
of the City of Oakdale.
[Amended 4-3-2023 by Ord.
No. 1284]
California Residential Code "Appendix Chapter" "H" is adopted.