Except as mains and other facilities may be extended or installed by the district on its own initiative and partially or wholly at its own expense, extensions of mains may be obtained by subdividers and others upon entering into a pipeline extension agreement prepared in accordance with the terms and conditions of Chapter 11.36 and 11.40, and not otherwise.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
Whether the district will enter into any particular pipeline extension agreement is a matter within the discretion of the board of directors. No pipeline extension will be approved or made unless and until the district can first determine that:
(1) 
It has sufficient water supply, line capacity and pressure in the existing system to serve the area involved;
(2) 
The taking on of additional services will not be detrimental to present or future district consumers;
(3) 
The project the extension will service has received final discretionary approval from the lead agency; and
(4) 
The pipeline extension will not violate any district rule, regulation, or policy.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
The district will determine sizes, materials, types and locations of all pipes, pumping plants, storage tanks and all other facilities necessary and required for proposed extension to the district's existing system. All system extensions and other facilities shall be installed by the district or under its supervision and to its specifications and in accordance with installation methods which it may approve. Unless the contrary is expressly agreed upon in writing, all materials shall be supplied by and all work shall be done by the district, either with its own forces or by a contractor selected or approved by it. The district's determination of cost and facilities required shall in all cases be final.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
No pipelines or other facilities shall be installed until such time as roadways are completed to subgrade and construction of curbs and gutters are completed.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
No pipelines or other facilities shall be installed until all pipeline rights-of-way, pumping plant sites and storage tank sites required for the installation, operation and maintenance of the facilities are furnished. The determination of the district as to requirements in each of these matters shall be final.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
Each application for pipeline extension and each pipeline extension agreement entered into pursuant thereto applies only to the parcel of land for which it is applied and/or approved and may not be transferred to any other parcel of land. By making application, the applicant agrees to abide by all district rules and regulations.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
When an application for a pipeline extension agreement is made by a person who is liable to the district for a liquidated amount for any fees or charges provided for in this code or by virtue of a contract with the district, under a judgment held by the district, or otherwise, the application may not be granted until the entire amount thereof is paid and credit established pursuant to Section 11.08.130, if applicable.
(Ord. 176 §1, 1978; Ord. 314 §2, 1990)
Services installed under pipeline extension agreements approved by the district since July 1, 1986 shall have eight years from the date of completion of facilities installed pursuant to said agreements, but not less than five years from January 1, 1992, to be put to the use for which application was made. If activation is not achieved in the time specified, the district will cause the service to be abandoned and will refund the connection fees, less the cost of abandoning the service, to the owner of record or his designee.
(Ord. 330 §3, 1992)