A.
With submittal of the application for final plan approval, the applicant shall provide one of the following performance guarantees for an amount adequate to cover the total costs of all required reclamation, taking into account the time span of the phasing, or reclamation schedule and the inflation rate for costs:
(1)
Either a certified check payable to the Town or a savings account or certificate of deposit naming the Town as owner, for the establishment of an escrow account; or
(2)
An irrevocable letter of credit from a financial institution, establishing funding for the construction or reclamation of the activity site, from which the Town may draw if reclamation or construction is inadequate, approved by the Selectmen.
B.
The conditions and amount of the performance guarantee shall be determined by the Planning Board with the advice of a licensed professional engineer, Town Road Commissioner, Town Selectmen, and/or Town Attorney at the cost of the applicant, if applicable.