[Ord. No. 1233, 6-21-2023]
A.
This policy is intended to implement, to the extent practical, the "Net Metering and Easy Connection Act," § 386.890, RSMo., et seq., and applicable Missouri Public Service Commission rules.
B.
Net metering and electrical system interconnection shall be made available on a first-come, first-served basis in the distribution service territory of City at any point on the Utility's existing facilities that has adequate capacity and suitable voltage for delivery of service until:
1.
The total rated generating capacity of all net metering systems on the utility equals five percent (5%) of the utility's single-hour peak load during the previous year; or
2.
The total rated generating capacity of approved new interconnection agreements during the current calendar year equals or exceeds one percent (1%) of the utility's single-hour peak load for the previous calendar year.