If it shall be necessary for any person, while removing a building, to have any utility relocated or removed, he shall give that utility at least forty-eight hours' notice thereof, whereupon it shall be the duty of the utility to remove, cut or change said utility facility and do all things necessary to attain the object for which removal is made, and the party moving such building shall pay the utility the going wage per hour, including benefits, for the actual time consumed by the utility in removing, cutting or changing such facility or doing anything in connection with the changing of such facility along with the cost of any materials and equipment used in such process.
(Ord. 1539 § 2 (part), 1983)