The following terms, when used within this chapter, shall have the following definitions:
"Adaptive management"is the process of monitoring and improving permits, regulations, and programs to ensure the protection of critical areas. A standard practice and systematic process used in natural resource management and protection, to ensure protective measures are effective, restoration or mitigation is successful, and natural resources are not depleted.
"Alteration"shall mean modification of soil or vegetation by any means including mechanical, chemical application, or hand work, in any area designated, or having the potential to be designated as a geologically hazardous area under the provisions of this chapter.
"Anadromous fish"means fish that spawn in fresh water and mature to the marine environment.
"Applicant"means a person who files an application for a permit under this chapter and who is either the owner of the land on which that proposed activity would be located, a contract purchaser, or the authorized agent of such person.
"Architect"shall mean a person licensed to practice architecture by the state of Washington.
"Buffer"means the zone contiguous with a critical area that is required for the continued maintenance, function, and structural stability of the critical area.
"City"means the city of Sultan.
"Clearing"means the destruction and removal of vegetation by any means and includes grubbing vegetation.
"Critical areas"means any of the following areas or ecosystems: critical aquifer recharge areas, fish and wildlife habitat conservation areas, frequently flooded areas, geologically hazardous areas, and wetlands as defined by the Growth Management Act (Chapter
36.70A RCW) and this chapter.
"Developable area"means areas outside of any critical area and their required setbacks or buffers.
"Development"means any man-made change to improved or unimproved real estate, including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials. "Development" also means subdivision of a parcel into one or more lots.
"Director"shall mean the community development director or his or her designee.
"Ecosystem functions"are the products, physical and biological conditions, and environmental qualities of an ecosystem that result from interactions among ecosystem processes and ecosystem structures. Ecosystem functions include but are not limited to, sequestered carbon, attenuated peak streamflow, aquifer water level, reduced pollutant concentrations in surface and ground waters, cool summer in-stream water temperatures, and fish and wildlife habitat functions.
"Ecosystem values"are the cultural, social, economic, and ecological benefits attributed to ecosystem functions
"Erosion"means the process by which soil particles are mobilized and transported by natural agents such as wind, rain, frost action, or stream flow.
"Erosion hazard area"means those areas of Sultan containing soils which, according to the USDA Soil Conservation Service, Snohomish County Soil Survey dated 1983, may experience severe to very severe erosion hazard.
"Fish and Wildlife Habitat Conservation Areas"are areas that serve a critical role in sustaining needed habitats and species for the functional integrity of the ecosystem, and which, if altered, may reduce the likelihood that the species will persist over the long term. These areas may include, but are not limited to, rare or vulnerable ecological systems, communities, and habitat elements including seasonal ranges, breeding habitat, winter range, and movement corridors, and areas with high relative population density and species richness. Fish and wildlife habitat conservation areas do not include such artificial features or constructs as irrigation delivery systems, irrigation infrastructure, irrigation canals, or drainage ditches that lie within the boundaries of, and are maintained by, a port district or an irrigation district or company.
"Flood fringe"means that portion of the floodplain outside of the floodway which is covered by floodwaters during the base flood; it is generally associated with standing water rather than rapidly flowing water.
"Flood" or "flooding"means a general and temporary condition of partial or complete inundation of normally dry land areas from the overflow of inland water and/or the unusual and rapid accumulation of runoff or surface waters from any source.
"Floodway"means the channel of a river or other watercourse and the adjacent land area that must be reserved in order to discharge the base flood without cumulatively increasing the surface water elevation more than one foot.
"Frequently Flooded Areas"means lands in the floodplain subject to at least a one percent or greater chance of flooding in any given year. These areas include, but are not limited to, streams, rivers, and lakes.
"General contractor"shall mean a bonded, insured and registered contractor in the state of Washington. A general contractor shall maintain state-required bonding and shall carry general liability insurance in the minimum amount of $1,000,000. The general contractor shall have a current valid state contractor's license with the state of Washington and a city of Sultan resident or nonresident business license, whichever is applicable.
"Geologist"means a practicing geologist licensed in the state of Washington as a licensed geologist in responsible charge, including experience with landslide evaluation.
"Geotechnical engineer"means a practicing geotechnical/civil engineer licensed as a professional civil engineer in the state of Washington as a geotechnical engineer in responsible charge, including experience with landslide evaluation.
"Hazard areas"means areas designated as frequently flooded or geologically hazardous areas due to potential for erosion, landslide, seismic activity, mine, collapse, or other geologically hazardous conditions.
"Hazard tree"is defined as a threat to life, property, or public safety. The method of hazard tree removal shall not adversely affect riparian ecosystem functions to the extent practicable. Additionally, the creation of snags (priority habitat features) shall be encouraged, rather than complete tree removal. Avoidance and minimization of damage to remaining trees and vegetation within riparian areas shall be enforced. A qualified arborist shall be required to evaluate requests for hazard tree removal.
"Impervious surface"means a hard surface area that either prevents or retards the entry of water into the soil mantle as under natural conditions prior to development or that causes water to run off the surface in greater quantities or at an increased rate of flow from the present under natural conditions prior to development. Common impervious surfaces include, but are not limited to, rooftops, walkways, patios, driveways, parking lots, storage areas, concrete or asphalt paving, gravel roads, packed earthen materials, and oiled macadam or other surfaces which similarly impede the natural infiltration of stormwater.
"Isolated wetland"means those wetlands that are outside of any not contiguous to any 100-year floodplain, lake, river, or stream and have no contiguous hydric soil or hydrophytic vegetation between the wetland and any surface water.
"Lake"means an area permanently inundated by water in excess of two meters deep and greater than 20 acres in size measured at the ordinary high water mark.
"Land surveyor"means a person who holds a Washington State land surveyor's license.
"Landform"means a geologic feature characterized by physical attributes such as elevation, slope, orientation, stratification, rock exposure, and soil type.
"Landslide hazard areas"means areas potentially subject to risk of mass movement due to a combination of geologic, topographic, and hydrologic factors.
"Lead design professional"means the person designated by the applicant to oversee and coordinate the permit review process on behalf of the applicant.
"Low impact development"is a stormwater and land use management strategy that strives to mimics the natural hydrologic conditions by emphasizing the pre-disturbance hydrologic process of infiltration, filtration, storage, evaporation and transpiration.
"Minimized" or "minimal"shall mean that the applicant has demonstrated to the satisfaction of the building official that the applicant has utilized best available science and commonly accepted engineering and architectural practice and has reduced, to the extent possible, the risks associated with development of the property.
"Minor utility project"means the placement of a utility pole, street sign, anchor, vault, or other small component of a utility facility, where the disturbance of an area is less than 75 square feet.
"Mitigation sequencing"means avoiding, minimizing, or compensating for adverse impacts on critical areas. Mitigation shall use any of the actions that are listed below in descending order of preference:
1. Avoiding the impact altogether by not taking a certain action or parts of an action; or
2. Minimizing impacts by limiting the degree or magnitude of the action and its implementation, by using appropriate technology, or by taking affirmative steps to avoid or reduce impacts; or
3. Rectifying the impact by repairing, rehabilitating, or restoring the affected critical areas; or
4. Reducing or eliminating the impact over time by preservation or maintenance operations during the life of the development proposal; or
5. Compensating for the impact by replacing, enhancing, or providing substitute critical areas; and
6. Monitoring the impacts and compensation project, and taking appropriate corrective measures. Mitigation for individual actions may include a combination of the above.
"Modified slope standard developments"means land within the boundaries of long plat subdivisions and short plats, granted final approval by the city of Sultan between October 26, 2006, and January 23, 2014.
"Monitoring"means the collection of data by various methods for the purpose of understanding natural systems and features, evaluating the impact of development proposals on such systems, and assessing the performance of mitigation measures imposed as conditions of development.
"Native growth protection easement (NGPE)"means an easement granted to the city of Sultan for the protection of native vegetation within a critical area or its associated buffer. The NGPE shall be recorded on the appropriate documents of title and filed with the Snohomish County recordings division.
"No net loss of critical areas"refers to the actions taken to achieve and ensure no overall reduction in existing ecological functions and values or the natural systems constituting the protected critical areas including the impacted or lost critical areas.
"Ordinary high water mark"means the mark that will be found by examining the bed and banks of a stream and ascertaining where the presence and action of waters are so common and usual, and so long maintained in all ordinary years, that the soil has a character distinct from that of the abutting upland, in respect to vegetation. In any area where the ordinary high water mark cannot be found, the line of mean high water shall substitute. In braided channels and alluvial fans, the ordinary high water mark or substitute shall be measured so as to include the entire stream feature.
"Practical alternative"means an alternative that is available and capable of being carried out after taking into consideration cost, existing technology, and logistics in light of overall project purposes, and having less impacts to critical areas.
"Priority habitat"means habitat types or elements with unique or significant value to one or more species as classified by the State Department of Fish and Wildlife.
"Project area"means all areas within 50 feet of the area proposed to be disturbed, altered, or used by the proposed activity or the construction of any proposed structures.
"Qualified professional"means a person with experience and training in the pertinent scientific discipline, and who has expertise appropriate to the relevant critical area subject in accordance with WAC
365-195-905(4). A qualified professional must have obtained a BS or BA or equivalent degree in biology, engineering, environmental sciences, fisheries, geomorphology, or a related field, and possess two years of related work experience.
A qualified professional for habitats must have a degree in biology or a related environmental science and professional experience related to the subject. |
A qualified professional for wetlands should be a person with professional wetland experience that meets the following criteria: |
a. | A Bachelor of Science or Bachelor of Arts or equivalent degree in hydrology, soil science, botany, ecology, resource management, or related field, or four years of full-time work experience as a wetland professional may substitute for a degree, and |
b. | At least two additional years of full-time work experience as a wetland professional; including delineating wetlands, preparing wetland reports, conducting function assessments, and developing and implementing mitigation plans, and |
c. | Completion of additional wetland-specific training programs. This could include a more comprehensive program such as the University of Washington Wetland Science and Management Certificate Program or individual workshops on topics such as wetland delineation, function assessment, mitigation design, hydrophytic plant or hydric soil identification. |
A person certified as a professional wetland scientist through the Society of Wetland Scientists professional certification program meets the above criteria. |
A qualified professional for geological hazards must be a professional engineer or geologist, licensed in the state of Washington. |
A qualified professional for critical aquifer recharge areas must be a hydrologist, geologist, engineer, or other scientist with experience in preparing hydrological assessments. |
"Reasonable use"means the minimum to which a property owner is entitled under applicable state and federal constitutional provisions, including takings and substantive due process.
"Site"means the entire area within the boundaries, as described in a legal description, of the property that is to be developed under the permit for which the applicant has applied.
"Slope"means the degree of tilt of a landform from the horizontal. A slope is delineated by establishing its toe and top and measured by averaging the inclination over at least 10 feet of vertical relief.
"Stable"shall mean that the risk of damage to the proposed development, or to adjacent properties, from soil instability is within the minimum safety factors for the static and seismic conditions of at least 1.5 and 1.15, respectively, and the building official has determined that the proposed development will not increase the potential for soil movement.
In order to meet the definition of "stable" the geotechnical report shall include identified hazards for the property and the mitigation measures proposed to reduce or correct the hazards along with measures taken to mitigate potential impacts from the remaining hazards, including all on- and off-site measures taken to correct or reduce the risk. These shall be fully disclosed to the applicant and future owners, heirs and assigns in the covenant required to be executed in accordance with provisions of this chapter, in which case the defined risk may be approved as an acceptable condition. |
"Stream"means water contained within a channel, either perennial or intermittent, and classified according to WAC
222-16-030 or
222-16-031 and as listed under "water typing system." Streams also include natural watercourses modified by man. Streams do not include irrigation ditches, or other wholly artificial watercourses, except those that directly result from the modification to a natural watercourse.
"Structural engineer"means a person licensed to practice structural engineering by the state of Washington.
"Structural fill"shall mean any fill placed below structures, including slabs, where the fill soils are intended to support loads without unacceptable deflections or shearing. Structural fill should be placed above unyielding native site soils compacted in accordance with an approved geotechnical report prepared utilizing best engineering science.
"Unavoidable"means adverse impacts that remain after all appropriate and practicable avoidance and minimization have been achieved.
"Understory"means the vegetation layer of a forest that includes shrubs, herbs, grasses, and grass-like plants, but excludes trees.
"Utility"means a service and/or facility that produces, transmits, carries, stores, processes, or disposes of electrical power, gas, potable water, storm water, communications (including, but not limited to, telephone and cable), sewage, oil and the like.
"Vegetation"means any and all organic plant life growing below, at, and above the soil surface.
Wetland edge.Delineation of the wetland edge shall be based on the approved federal wetland delineation manual and applicable regional supplements or as revised.
Wetland rating systemWetlands shall be rated according to the Washington State Wetland Rating System for Western Washington, Department of Ecology 2014 Update, Version 2.0, Publication No. 23-06-009 or as revised.
(Ord. 1197-14 § 1; Ord. 1210-15 § 1; Ord. 1257-17 § 1 (Exh. A); Ord. 1347-21 § 43; Ord. 1419-25, 7/24/2025)