The side sewer contractor before beginning in a public area shall have at the site sufficient barricades to properly protect the work. The barricades shall be illuminated during the nighttime hours with a minimum of four flares or flashing signals.
(Ord. 154 § 16.01, 1974)
During the pipe laying operation, a ditch pump shall be available at the site. The contractor shall have stockpiled, within the City and immediately available for use, sufficient shoring to adequately protect workmen where unstable ground conditions are encountered.
(Ord. 154 § 16.02, 1974)
In addition to the foregoing provisions, the side sewer contractor shall comply with all laws, ordinances and regulations of Washington State, Whatcom County or the City of Everson, relating to the safety and protection of the area affected. A flagman must be posted wherever work is underway within the public right-of-way.