Section J105 is hereby amended, by the deletion of the entire section and the addition of a new section thereto, to read as follows:
Section J105.1 General is added to read as follows:
J105.1 General. Grading inspections shall be governed by Section 109, Appendix Chapter J108 of this code and as indicated herein. Grading operations for which a permit is required shall be subject to inspection by the City Engineer. In addition, professional inspection of grading operations shall be performed by the Field Engineer, Soils Engineer and the Engineering Geologist retained to provide such services in accordance with this Section for engineered grading and as required by the City Engineer for regular grading. |
Section J105.2 Special and Supplemental inspections is added to read as follows:
J105.2 Special and Supplemental inspections. The special inspection requirements of Section 1704.7 shall apply to work performed under a grading permit where required by the City Engineer. In addition to the called inspections specified in Section 105.7, the City Engineer may make such other inspections as may be deemed necessary to determine that the work is being performed in conformance with the requirements of this code. The City Engineer may require investigations and reports by an approved soil testing agency, Soils Engineer and/or Engineering Geologist, and Field Engineer. Inspection reports shall be provided when requested in writing by the City Engineer. |
The City Engineer may require continuous inspection of drainage devices by the Field Engineer in accordance with this section when the City Engineer determines that the drainage devices are necessary for the protection of the structures in accordance with Section 110 of this code. |
Section J105.3 Field Engineer is added to read as follows:
J105.3 Field Engineer. The Field Engineer shall provide professional inspection of those parts of the grading project within such engineer's area of technical specialty, oversee and coordinate all field surveys, set grade stakes, and provide site inspections during grading operations to ensure the site is graded in accordance with the approved grading plan and the appropriate requirements of this code. During site grading, and at the completion of both rough grading and final grading, the Field Engineer shall submit statements and reports as required by Sections J105.11 and J105.12. If revised grading plans are required during the course of the work they shall be prepared by a Civil Engineer and approved by the Building Official. |
Section J105.4 Soils Engineer is added to read as follows:
J105.4 Soils Engineer. The Soils Engineer shall provide professional inspection of those parts of the grading project within such engineer's area of technical specialty, which shall include observation during grading and testing for required compaction. The Soils Engineer shall provide sufficient observation during the preparation of the natural ground and placement and compaction of the fill to verify that such work is being performed in accordance with the conditions of the approved plan and the appropriate requirements of this chapter. If conditions differing from the approved soils engineering and engineering geology reports are encountered during grading, the Soils Engineer shall provide revised recommendations to the permittee, the City Engineer and the Field Engineer. |
Section J105.5 Engineering Geologist is added to read as follows:
J105.5 Engineering Geologist. The Engineering Geologist shall provide professional inspection of those parts of the grading project within such engineer's area of technical specialty, which shall include professional inspection of the bedrock excavation to determine if conditions encountered are in conformance with the approved report. If conditions differing from the approved engineering geology report are encountered, the Engineering Geologist shall provide revised recommendations to the soils engineer. |
Section J105.6 Permittee is added to read as follows:
J105.6 Permittee. The permittee shall be responsible for ensuring that the grading is performed in accordance with the approved plans and specifications and in conformance with the provisions of this code. The permittee shall engage project consultants, if required under the provisions of this code, to provide professional inspections on a timely basis. |
The permittee shall act as a coordinator between the project consultants, the contractor and the City Engineer. In the event of changed conditions, the permittee shall be responsible for informing the City Engineer of such change and shall provide revised plans for approval. |
Section J105.7 Required Inspections is added to read as follows:
J105.7 Required Inspections. The permittee shall call for an inspection by the City Engineer at the following various stages of work and shall obtain the approval of the City Engineer prior to proceeding to the next stage of work: |
Pre-grade. Before any construction or grading activities occur at the site. Permittee shall schedule a pregrade inspection with the City Engineer. The permittee shall ensure that all project consultants are present at the pre-grade inspection. |
Initial. When the site has been cleared of vegetation and unapproved fill and has been scarified, benched or otherwise prepared for fill. No fill shall have been placed prior to this inspection. |
Rough. When approximate final elevations have been established; drainage terraces, swales and other drainage devices necessary for the protection of the building sites from flooding have been installed; berms have been installed at the top of the slopes; and the statements required by Section J105.12 have been received. |
Final. When grading has been completed; all drainage devices necessary to drain the building pad have been installed; slope planting has been established, irrigation systems have been installed; and the as-built plans and required statements and reports have been submitted. |
Section J105.8 Notification of Noncompliance is added to read as follows:
J105.8 Notification of Noncompliance. If, in the course of fulfilling their respective duties under this chapter, the Field Engineer, the Soils Engineer or the Engineering Geologist determines that the work is not being done in conformance with this chapter or the approved grading plans, the Field Engineer, Soils Engineer or the Engineering Geologist shall immediately report, in writing, the discrepancies and the recommended corrective measures to the permittee and to the City Engineer. |
Section J105.9 Transfer of Responsibility is added to read as follows:
J105.9 Transfer of Responsibility. If the Field Engineer, the Soils Engineer, or the Engineering Geologist of record is changed after grading has commenced, the City Engineer may stop the grading until the permittee has identified a replacement and the replacement has agreed in writing to assume responsibility for those parts of the grading project that are within the replacement's area of technical competence. It shall be the duty of the permittee to notify the City Engineer in writing of such change prior to the recommencement of such grading. |
Section J105.10 Non-inspected grading is added to read as follows:
J105.10 Non-inspected grading. No person shall own, use, occupy or maintain any non-inspected grading. For the purposes of this code, non-inspected grading shall be defined as any grading for which a grading permit was first obtained, pursuant to Section J103, supra, but which has progressed beyond any point requiring inspection and approval by the City Engineer without such inspection and approval having been obtained. |
Section J105.11 Routine Field Inspections and Reports is added to read as follows:
J105.11 Routine Field Inspections and Reports. Unless otherwise directed by the Building Official, the Field Engineer for all engineered grading projects shall prepare routine inspection reports and shall file these reports with the City Engineer as follows: |
1. | Bi-weekly during all times when grading of 400 cubic yards or more per week is occurring on the site; |
2. | Monthly, at all other times; and |
3. | At any time when requested in writing by the City Engineer. |
Such reports shall certify to the City Engineer that the Field Engineer has inspected the grading site and related activities and has found them in compliance with the approved grading plans and specifications, the building code, all grading permit conditions, and all other applicable ordinances and requirements. The reports shall conform to a standard "Report of Grading Activities" form which shall be provided by the City Engineer. |
Section J105.12 Completion of work is added to read as follows:
J105.12 Completion of work. Upon completion of the rough grading work and at the final completion of the work, the following reports and drawings and supplements thereto are required for engineered grading or when professional inspection is otherwise required by the City Engineer: |
1. | An "As-Built" grading plan prepared by the Field Engineer retained to provide such services in accordance with Section J105.3 showing all plan revisions as approved by the City Engineer. This shall include original ground surface elevations, as-built ground surface elevations, lot drainage patterns, and the locations and elevations of surface drainage facilities and the outlets of subsurface drains. As-built locations, elevations and details of subsurface drains shall be shown as reported by the soils engineer. The As-Built grading plan shall be accompanied by a certification by the Field Engineer that to the best of his or her knowledge, the work within the Field Engineer's area of responsibility was done in accordance with the final approved grading plan. |
2. | A report prepared by the Soils Engineer retained to provide such services in accordance with Section J105.4, including locations and elevations of field density tests, summaries of field and laboratory tests, other substantiating data, and comments on any changes made during grading and their effect on the recommendations made in the approved soils engineering investigation report. The report shall include a certification by the Soils Engineer that, to the best of his or her knowledge, the work within the Soils Engineer's area of responsibility is in accordance with the approved soils engineering report and applicable provisions of this chapter. The report shall contain a finding regarding the safety of the completed grading and any proposed structures against hazard from landslide, settlement, or slippage. |
3. | A report prepared by the Engineering Geologist retained to provide such services in accordance with Section J105.5, including a final description of the geology of the site and any new information disclosed during the grading and the effect of such new information, if any, on the recommendations incorporated in the approved grading plan. The report shall contain a certification by the Engineering Geologist that, to the best of his or her knowledge, the work within the Engineering Geologist's area of responsibility is in accordance with the approved engineering geology report and applicable provisions of this chapter. The report shall contain a finding regarding the safety of the completed grading and any proposed structures against hazard from landslide, settlement, or slippage. The report shall contain a final as-built geologic map and cross-sections depicting all the information collected prior to and during grading. |
4. | The grading contractor shall certify, on a form prescribed by the City Engineer, that the grading conforms to said as-built plan and the approved specifications. |
Section J105.13 Notification of completion is added to read as follows:
J105.13 Notification of completion. The permittee shall notify the City Engineer when the grading operation is ready for final inspection. Final approval shall not be given until all work, including installation of all drainage facilities and their protective devices, and all erosion-control measures have been completed in accordance with the final approved grading plan, and all required reports have been submitted and approved. |
Section J105.14 Change of Ownership is added to read as follows:
J105.14 Change of Ownership. Unless otherwise required by the City Engineer, when a grading permit has been issued on a site and the owner sells the property prior to final grading approval, the new property owner shall be required to obtain a new grading permit. |