(A)
Applicability. The storage and controlled release rate of excess stormwater runoff shall be required for any redevelopment or other new construction located within the City of Angola city limits if soil disturbance greater than or equal to one acre is proposed and operations that result in the land disturbance of less than one acre of total land area that are part of a larger common plan of development or sale.
(B)
Exemptions for Detention Requirements. Detention will not be required for the following:
(1)
Land alterations for the construction, enlargement, or location (on a permanent foundation) of a one-family dwelling, two-family dwelling, or accessory structure appurtenant to either a one- or two- family dwelling; notwithstanding the requirements for an individual lot plot plan permit in this chapter.
(2)
Land-disturbing activities where there will be no additional impervious surfaces associated with the final completed project, including, but not limited to, ditch construction/reconstruction and utility installation/maintenance activities.
(3)
Notwithstanding the provisions of AMC § 13.15.510, those site developments where the stormwater management system has been designed such that:
(a)
After combining flows from both the off-site and on-site drainage areas, there will be no increase in the total peak discharge from the developing site during the two-, 10-, and 100-year storm events; and
(b)
The volume of runoff for each project site outlet has not been increased for the two-, 10- and 100-year storm events; and
(c)
The flow width and velocity at the property boundary line of each subbasin is less than or equal to that flow width and velocity which existed prior to the development for the two-, 10-, and 100-year storm events.
(Ord. 1751-2024)