A.
Prior to submittal of applications for Type II, III and IV project permit actions, applicants will schedule a pre-application conference; provided, however, that this pre-application conference requirement may be waived by the administrator when staff and the applicant agree that a meeting is unnecessary. Pre-application conferences for all other types of applications are optional on the part of the applicant. The purpose of the pre-application conference is to acquaint the applicant with the requirements of the RMC, and to familiarize city staff with the details of the potential project application.
B.
The conference shall be held within 21 calendar days of the request.
C.
At the conference or within five working days of the conference, the applicant may request that the following be provided:
1.
A form which lists the requirements for a completed application;
2.
A general summary of the procedures to be used to process the application;
3.
The references to the relevant code provisions or development standards which may apply to the approval of the application; and
4.
The city's design guidelines.
D.
The conference is not to be construed by the applicant as an exhaustive review of all potential issues. The discussions at the conference, or the information sent by the city to the applicant under subsection (C) of this section, shall not bind or prohibit the city's future application or enforcement of all applicable law.
(Ord. 12-96; Ord. 29-12 § 1.01; Ord. 21-19 § 1)