A.
The following public improvements will be required
and bonded if applicable:
(1)
Street pavement.
(2)
Curbs and sidewalks.
(3)
Streetlights.
(4)
Storm drainage facilities, including landscaping and
fencing of recharge basins.
(5)
Street signs to conform to existing Village standards.
(6)
Street trees.
(7)
Bulkheading where necessary and subject to special
regulations and controls.
(8)
Water mains and underground electric lines.
(9)
Fire wells or cisterns.
B.
The following public utilities may be required but
not bonded by the Village. Assurance of construction from the appropriate
private company or public agency must be supplied to the Planning
Board by the subdivider.
C.
Public improvements for which the subdivider has been bonded shall be constructed in accordance with Article X, Design Standards, and with the construction specifications for subdivisions as adopted by the Village Board. Said specifications shall be drawn up by the Village Engineer, and the Village Engineer shall be the enforcement officer thereof.
D.
Fire wells shall be installed according to the specifications
of the Fire Department, such specifications to be on file at the office
of the Planning Board. Upon completion of the installations, the subdivider
shall contact the Fire Department so that a representative of the
Department may arrange any appropriate tests of the well before acceptance.
A.
All bonded improvements shall be inspected by the
Village Engineer to ensure satisfactory completion.
B.
At least 24 hours' notice shall be given to the Village
Engineer prior to any major construction or installation so that a
representative of the Village may be present at the time the work
is performed.
C.
The subdivider shall supply the Village Engineer with
a schedule of construction indicating the beginning and completion
dates of each of the following phases of work:
D.
The subdivider shall notify the Village Engineer,
in writing, at least five days prior to the completion of each of
the above phases of construction.
E.
Construction testing of roadway pavement materials
shall be performed in accordance with the requirements of the road
and drainage standards for the Village of Southampton.
G.
A final inspection of all improvements shall be made
by the Village Engineer to determine whether the work is satisfactory
and in substantial agreement with the approved final plat drawings,
design standards of these regulations and the construction specifications
for subdivisions. The general condition of the site shall also be
considered. If erosion conditions exist or it appears likely that
a hazardous or unsatisfactory condition may arise, the Village Engineer
may require special measures be taken by the subdivider.
[Amended 11-10-1994 by L.L. No. 11-1994]
A.
A review fee shall be required for review of proposed subdivisions which involve new road construction. The amount of such fee shall be as specified in § 97-47.
C.
If a subdivision is abandoned, no part of the inspection
or review fees already paid to the Village will be returned to the
subdivider.