A progress schedule of all proposed subdivision
work shall be submitted by the subdivider. The schedule shall indicate
the estimated commencement and completion dates for the major items
of work involved in the project. The schedule shall be reviewed by
the Superintendent of Highways and the Town Engineer for approval.
Upon approval, or approved as corrected, the work shall be adhered
to by the subdivider for the orderly performance and completion of
the work.
The flow of traffic or the safety thereof on
any public street or highway within the Town shall not be restricted
or endangered in any way by construction operations, equipment, vehicles
or materials connected with road construction by subdivision development.
Stormwater runoff from developments must be
confined to the site unless adequate facilities exist. Methods of
providing temporary drainage shall be approved by the Town Engineer.
Rainfall runoff onto roads, streets or private property is prohibited.
All drainage facilities during construction
shall be cleared of lumber debris, dirt or other objectionable material
after completion and shall be maintained in a clean condition until
time for use.
Topsoil removal is prohibited. Refer to Chapter
228, Soil Removal, of the Southold Town Code regarding soil removal.