[Amended 7-7-1982; 9-7-1993 by Ord. No. 5-1993]
A concept plan of a major subdivision may be submitted for discussion before the preliminary plat is prepared. This step is recommended by the Planning Board. As its name indicates, the concept plan is designed to enable the Planning Board and the applicant to discuss principles involved before the applicant has gone to the expense of completing detailed engineering drawings. The Planning Board will provide guidance; however, this guidance will not be binding upon the developer, the Township or the Planning Board and may be subject to change. It is designed to enable the applicant to proceed on a reasonably sound basis. It should be emphasized that concept approval does not carry the authority to proceed with construction, nor does it necessarily guarantee approval of a preliminary plat submitted in accordance with this chapter. Where disturbance of environmentally sensitive areas would result from collection of soils or other pertinent data, the opinion of the Board shall be solicited as to the mitigation of such disturbance prior to its occurrence.
A. Any developer in the Township requesting approval of a proposed concept plat of a major subdivision shall, prior to subdividing or resubdividing land as designated in this chapter, submit the following to the Secretary of the Planning Board at least 28 days prior to the regular Planning Board meeting:
(1) Twelve copies of the concept plat of the proposed major subdivision.
(2) Three copies of the application on forms to be obtained from the Secretary of the Planning Board.
B. The Secretary of the Planning Board shall mark each copy with the appropriate application number and the person to receive such copy and shall forward copies of the plat, together with a form requesting return of the plat with comment within 14 days, to the following:
(1) Subdivision/Site Plan Committee.
(5) Environmental Commission.
(8) Public Works Department.
[Added 7-18-1994 by Ord. No. 5-1994]
C. One copy will be on file in the office of the Planning Board Secretary for public inspection.