The conditions of any permit issued by the Town to an industrial
user will be subject to the provisions and requirements of this chapter,
all applicable federal and state pretreatment standards and requirements
and applicable requirements of the receiving sewer agencies.
Permits issued by the Town shall be valid for a period of three
years. Users shall apply for permit renewal a minimum of 180 days
prior to their permit expiration date.
As EPA, DEC or another appropriate enforcement agency adds or
amends specific pretreatment and effluent guidelines, or as the Town
deems necessary, the restrictions or conditions of any WSPDES permit
may require the introduction of changes or amendments, as circumstances
dictate. When necessary, the Town shall require an industrial user
to develop a time schedule for the installation of technology to comply
with all applicable federal, state and local pretreatment standards
and requirements. In the event that an existing user becomes subject
to a newly promulgated national categorical pretreatment standard,
that user shall submit a report to the Town within 180 days of promulgation
of any applicable federal categorical pretreatment standard, describing
the nature and concentration of any and all substances contained in
the existing discharge which are impacted by the categorical standard.
This report shall further specify whether the existing discharge complies
with the categorical standard and, if not, shall provide a schedule
for incorporation of additional pretreatment necessary to comply.