Before the Township shall allow any building permits to be issued after approval of the final plan of any subdivision or land development (except in the case of minor subdivisions wherein the Supervisors impose no conditions for the approval of the plan, or in the case of a waiver from the land development process), the owners shall enter into a written agreement with the Township in the manner and form set forth by a standard contract, wherein they shall agree:
A.
To construct or cause to be constructed, at the owner's expense, all streets, curbs, sidewalks, water and sewer mains, fire hydrants, streetlights, drainage facilities, street signs, monuments, parks, landscaping, recreation facilities and other improvements shown on said final plan when required to do so by the Board of Supervisors, in accordance with the approved final plan in strict accordance with the standards and specifications of the Township.
B.
To maintain, at the owner's cost, the said improvements until the same are accepted by the Township for public use, and for a period of 18 months thereafter to repair and reconstruct the same or any part of one of them when such repair or reconstruction shall be specified by the Board of Supervisors as necessary by reason of faulty construction, workmanship or materials, at or before acceptance of such improvements by the Township.
C.
To pay all costs, charges or rates of the utility furnishing electric service for the lighting of the streets on or abutting said subdivision, from the lights installed by the owner, until such time as the streets shown on the subdivision plans shall be accepted as public streets of the Township by resolution approved by the Court of Common Pleas and to indemnify and save harmless the Township from and against all suits, actions, claims and demands for electric service to the streets shown on said plans or any part thereof to the time that the said streets shall be accepted as public streets of the Township in the manner hereinabove set forth.
E.
To obtain the easements and releases required when any street, drainage facility or other improvement in a subdivision abuts or traverses lands of persons other than the person holding legal title to the lands of the subdivision at his own cost, and obtain from the owner of the lands so abutted or traversed full releases from all damages which may result from a change in grade, construction or otherwise of the street, drainage facility or other improvement, and such releases shall inure to the benefit not only of the owner of the subdivision but to the Township as well. The easements and releases must be recorded before the plan is recorded.