Exciting enhancements are coming soon to eCode360! Learn more 🡪
Kent County, DE
 
By using eCode360 you agree to be legally bound by the Terms of Use. If you do not agree to the Terms of Use, please do not use eCode360.
Table of Contents
Table of Contents
The following items shall be completed during the interconnection of multisection homes when the manufacturer's installation instructions are not available.
A. 
Provide an air infiltration barrier on the matting edges of the floor, end walls and ceilings.
B. 
If accessible, fasten the roof at the ridge with No. 10 by four-inch wood screws, at a minimum, at twelve-inch, on center, staggered intervals. If the ridge is not accessible use .027 minimum thickness metal straps across the ridge to connect each of the opposing structural members.
C. 
Secure end walls with No. 10 by four-inch wood screws, at a minimum, at six-inch, on center, staggered intervals. Fasten floors together at the mating line with No. 10 by four-inch wood screws, at a minimum, at twelve-inch, on center, staggered intervals.
D. 
Mating walls shall be firestopped in accordance with the MHCSS.
Normal Home Installations
(Single or Multisection Homes)
Types of Foundation Systems - Main Components
Piers-Ground anchors: The manufactured home rests on piers of concrete block; formed-in-place concrete; permanent wood; or steel pedestals on permanent wood, crushed stone or concrete footers. The ground anchors in the soil are angled to the resist straps or embedded in dead-men in the soil. Straps are tied to the frame, with or without over-the-top straps.
Concrete slab or continuous footings: The manufactured home rests on a concrete slab or ribbons of concrete. The straps are tied between the frame and the perimeter footers or concrete slab.
Pile/post system: The manufactured home rests on piles or posts placed sufficiently deep in the ground to resist all wind, snow and earthquake forces. Straps fasten the home to the piles or posts or to caps placed thereon.
Concrete, concrete block or wood foundation, load-bearing, perimeter walls: The manufactured home rest on exterior load-bearing walls that sit on concrete or gravel footings. Straps fasten the home to the walls to resist all external forces.
After blocking and leveling, the installer should secure the manufactured home against the wind. The type of installation is the determining factor in deciding how this should be done, as is described in the following sections.
A. 
Normal installations. Section 156-16 summarizes and defines the types of normal installations. The pier-and-ground-anchor system, as provided in this chapter, is most common. When using another type of installation, consult a registered engineer. (NOTE: The anchoring or foundation system shall be capable of meeting the loads required by the MHCSS.)
(1) 
Number and location of anchors. The number and location of straps and anchors is determined by the size of the home. The anchors shall be spaced not more than two feet zero inches from each end of the home and not more than 11 feet zero inches apart unless the anchor manufacturer specifies a greater spacing. Use either the single- or the double-strap method. Use only approved ground anchors capable of resisting at least 4,725 pounds.
(2) 
Installation of anchors. The following is one example: Install the anchors at the locations selected from Figure 5-2[1] when the home manufacturer's installation instructions are not available. Follow the anchor manufacturer's instructions. Use single-headed anchors at all "frame-tie-only" locations when using the single-strap method, and double-headed anchors when employing the double-strap method. Install single- or double-headed anchors at all over-the-roof-tie locations. When using a single strap, line up the shaft of each anchor with its strap (see Figure 5-3[2]). When connecting more than one strap to a single anchor, line the shaft of the anchor with the results achieved by calculating the combined forces (see Figure 5-4[3]). The ground anchors must be sized for the direction of the load and the type of soil. (See Figures 5-3 and 5-4 for additional information of the installation of anchors and tiedowns.)
[1]
Editor's Note: Figure 5-2 is included at the end of this chapter.
[2]
Editor's Note: Figure 5-3 is included at the end of this chapter.
[3]
Editor's Note: Figure 5-4 is included at the end of this chapter.
B. 
Over-the-roof straps. If over-the-roof straps are provided with the home, they must be installed.
C. 
Severe climatic conditions.
(1) 
Freezing. Be sure anchor augers are installed below 24 inches below grade. During periods of frost heave, be prepared to lessen tension on the straps.
(2) 
Areas prone to flooding. Foundation considerations are discussed in § 156-15A and the FEMA document referenced in Appendix A. Unconventional anchorage and tie-downs often are needed in designing and constructing and special elevated foundations required in areas prone to flooding. Consult an engineer and the Kent County Department of Inspections and Enforcement for guidance.
Site-constructed porches must be constructed and inspected according to the CABO Building Code adopted by Kent County.
A. 
Steps and stairways.
(1) 
When risers are closed, all treads may have a uniform projection not more than 1 1/2 inches.
(2) 
The greatest riser height within any flight of stairs shall not exceed the smallest by more than 3/8 inch. The greatest tread run within any flight of stairs shall not exceed the smallest by more than 3/8 inch.
(3) 
Stairways shall not be less than three feet in clear width, with a maximum rise of 8 1/4 inches and a minimum tread run of nine inches.
B. 
Handrails and guardrails.
(1) 
Handrails. Handrails having minimum and maximum heights of 30 inches and 38 inches, respectively, measured vertically from the nosing of the treads, shall be on at least one side of stairs of three or more risers. The handgrip portion of the handrails shall not be more than 2 5/8 inches in cross-sectional dimension, or the shape shall provide an equivalent gripping surface. The handgrip portion of the handrails shall have a smooth surface with no sharp corners. Handrails projecting from a wall shall have not less than 1 1/2 inches between the wall and the handrail.
(2) 
Guardrails. Porches or decks located more than 30 inches above the floor or grade below shall have guardrails not less than 36 inches in height. Open sides of stairways with a total rise of more than 30 inches above the floor or grade below shall have guardrails not less than 34 inches in height measured vertically from the nosing of the treads. Required guardrails on open sides of stairways, raised floor areas, porches and decks shall have intermediate rails or ornamental enclosures which will not allow the passage of an object six inches or more in diameter.
Install expanding rooms in accordance with the manufacturer's instructions. When the manufacturer's instructions are not available, perimeter blocking shall be installed in accordance with Table 4-1; ground anchors shall be installed in accordance with Figure 5-2.[1]
[1]
Editor's Note: Table 4-1 and Figure 5-2 are included at the end of this chapter.