The following public improvements will be required and bonded, except where these subdivision regulations specifically waive the requirement or when the Planning Board waives the requirement by specific resolution:
(1) 
Street pavement.
(2) 
Curbs.
(3) 
Sidewalks.
(4) 
Storm drainage facilities.
(5) 
Street signs.
(6) 
Street trees.
(7) 
Water mains.
(8) 
Fire hydrants as specified by the Fire Commission (only when water mains are to be installed).
(9) 
Sewage disposal facilities as specified by the County Health Department and other appropriate agencies.
(10) 
Streetlights.
B. 
Public improvements for which the subdivider has been bonded shall be constructed in accordance with the construction specifications for subdivisions as adopted by the Municipal Board. Said specifications shall be drawn up by the Municipal Engineer for street illumination and sanitation facilities. The Municipal Engineer shall be the Enforcement Officer thereof.
A. 
All public improvements shall be inspected by the Municipal Engineer to ensure satisfactory completion.
B. 
At least 24 hours' notice shall be given to the Municipal Engineer prior to any major construction or installation so that a representative of the municipality may be present at the time the work is performed.
C. 
The Municipal Engineer shall be notified after each of the following preparatory phases of the work has been completed so that a representative of the municipality may inspect the work:
(1) 
Road subgrade.
(2) 
Curb forms.
(3) 
Sidewalk forms.
(4) 
Drainage pipe and other drainage structures, before backfilling.
(5) 
Water mains and hydrant connections, prior to backfilling.
D. 
A final inspection of all improvements shall be made by the Municipal Engineer to determine whether the work is satisfactory and in substantial agreement with the approved final plat drawings and the construction specifications for subdivisions. The general condition of the site shall also be considered.
E. 
Testing of completed sewage facilities, with reports to the Westchester County Department of Health, shall be performed by a professional engineer at the expense of the developer.
[Amended 2-21-2007 by L.L. No. 1-2007]
An inspection fee in the amount as set forth in the most current resolution of the Town Board fixing the fee pursuant to § 137-1 of the Town Code shall be paid to the municipality prior to the time that the Chairman or Vice Chairman of the Planning Board signs the final plat. If the public improvements are to be installed without the posting of a bond, the inspection fee shall be as set forth in the most current resolution of the Town Board fixing the fee pursuant to § 137-1 of the Town Code.