Action. The Commission shall determine whether the
proposed construction, reconstruction, alteration, moving or demolition
is appropriate or inappropriate within 30 days of the public hearing
or within 45 days of the receipt of the completed application, whichever
comes first. If the Commission determines the proposal is appropriate,
it shall immediately approve a certificate of appropriateness and
return it to the Code Enforcement Officer for issuing of the necessary
permits. If the Commission determines that a certificate of appropriateness
should not be issued, it shall advise the applicant, in writing, through
the Code Enforcement Officer, of any changes which would secure the
approval of the Commission and withhold denial for 30 days, in order
that the applicant may adopt such proposed changes. The Code Enforcement
Officer shall notify the applicant of the decision and furnish him
a copy of the reasons and the recommendations, if any, as appearing
in the records of the Commission.