A. 
The required land improvements shall be designed, furnished, and installed by the developer in accordance with the provisions of these regulations, the Horsham Township Construction Standards as adopted by this chapter (provided in the attachment section of the chapter),[1] which shall be considered a part hereof, and other codes of the Township. They shall be installed before the final plan is approved, or in lieu thereof, financial security shall be posted.
[1]
Editor's Note: The Horsham Township Construction Standards are included at the end of this chapter.
B. 
The developer shall dedicate all land required for rights-of-way and easements within the subdivision and land development, and furnish and install all improvements to provide a complete and coordinated system of streets and utilities for the neighborhood, in accordance with the Township Comprehensive Plan; the Township Official Map; Chapter 230, Zoning; this chapter; and neighboring approved developments.
All improvements shall be dedicated without cost to the Township as required by this chapter and/or as stipulated in the improvements agreement and in a manner approved by the Township consistent with sound construction methods. This includes:
A. 
Grading.
(1) 
Grading of roadways and street rights-of-way and grading of slopes adjacent to roadways and street rights-of-way.
(2) 
Grading of all drainage swales on public or private property and grading of individual lots, to establish positive drainage away from buildings and eliminate low spots.
(3) 
Implementation and maintenance of soil erosion control and sedimentation control facilities.
(4) 
Replacement of topsoil and vegetative restoration in disturbed areas not stabilized with building, paving or other nonvegetative ground cover.
(5) 
Removal of temporary soil erosion and sedimentation control facilities when they are no longer required.
B. 
Street or road subbase, base and paving.
C. 
Curbs and driveway aprons.
D. 
Sidewalks, crosswalks, pathways and bike paths.
E. 
Underground facilities for electric, telephone and television cable lines.
F. 
Storm sewers, drainage facilities and easements.
G. 
Public sanitary sewer system.
H. 
Public or centralized water supply and distribution system including but not limited to wells, pumping equipment, water laterals, submains, storage tanks and equipment systems (if required).
I. 
Street name signs at all street intersections and official traffic control signs and markings.
J. 
Permanent monuments and lot pins.
K. 
Fire hydrants and markers.
L. 
Street trees and appurtenances; landscaping.
M. 
Open space improvements and/or recreational facilities, buffer or screen plantings.
N. 
Streetlights.
A. 
The developer shall construct and install, at no expense to the Township, the improvements specified in this chapter. Construction and installation of such facilities and utilities shall be subject to inspection by appropriate Township, public agency or public utility officials during the progress of the work and shall be in conformance with the Horsham Township Construction Standards.
B. 
During the construction and installation of all facilities and utilities required by this chapter, the developer shall insure that access to the job site from a public road shall be kept clear and free of all obstructions and otherwise in a passable condition to all areas of the job site for emergency, fire, and police vehicles. In the event of a dispute, passable access for the foregoing purposes shall be determined by the Township.
C. 
The Township Engineer shall be authorized to have such tests of materials completed as deemed necessary in order to verify suitability of materials. Where such tests are not completed by the developer, the Township shall have these tests completed and the owner shall pay to the Township the cost of such tests plus 15%.
D. 
Developer shall agree that during the course of construction, and once there is at least one occupant in the subdivision or development, developer will provide for the plowing of snow on subdivision or land development roads as may be necessary to provide ingress and egress to the occupant(s), at developer's cost. The snow plowing shall be done whenever Township roads are plowed by the Township.
The following principles of subdivision and land development, general requirements and the minimum standards of design shall be observed by the developer in all instances:
A. 
It is the developer's responsibility to comply with all applicable plans, ordinances, statutes, regulations, etc., of Horsham Township, Montgomery County, Commonwealth of Pennsylvania, and the United States of America.
B. 
Proposed subdivisions and land developments shall be coordinated with existing nearby development so that the area as a whole may develop harmoniously. Provision shall be made to assure that the street patterns included in a proposed subdivision shall complement existing or proposed streets shown on the current official Township Street and Road Map, and on nearby approved developments.
C. 
Standards incorporated in this chapter. In those cases where precise design standards are not specified in this chapter, or other ordinance adopted by Horsham Township, design standards of the following organizations shall govern where applicable:
(1) 
Roads and streets: Pennsylvania Department of Transportation, American Association of State Highway and Transportation Officials, Institute of Transportation Engineers, Transportation Research Board, U.S. Department of Transportation, Federal Highway Administration, and Horsham Township.
(2) 
Sanitary sewer: Pennsylvania Department of Environmental Protection, Montgomery County Department of Health, and servicing municipal authority.
(3) 
Water: Pennsylvania Department of Environmental Protection, Montgomery County Department of Health, Delaware River Basin Commission, and servicing municipal authority.
(4) 
Soil and erosion control: Montgomery County Conservation District, Department of Environmental Protection, U.S. Department of Agriculture Soil Conservation Service, and Horsham Township.
(5) 
General engineering: American Society of Civil Engineers, Army Corps of Engineers, Federal Emergency Management Association, Horsham Township Engineer and Horsham Township.
No plat shall be finally approved unless the streets shown on such plat have been improved as required by this chapter, and any walkways, curbs, streetlights, fire hydrants, trees, water mains, sanitary sewers, storm sewers and other improvements as may be required by this chapter have been installed in accordance with this chapter.
A. 
In lieu of the completion of any improvements required as a condition for the final approval of a plat, including improvements or fees required pursuant to Section 509(i) of the Municipalities Planning Code,[1] this chapter shall provide for the deposit with the municipality of financial security in an amount sufficient to cover the costs of such improvements or common amenities including, but not limited to, roads, stormwater detention and/or retention basins and other related drainage facilities, recreational facilities, open space improvements, or buffer or screen plantings which may be required.
[1]
Editor's Note: See 53 P.S. § 10509(i).
B. 
When requested by the developer, the governing body shall furnish the developer with a signed copy of a resolution or letter of contingent approval indicating approval of the final plat contingent upon the developer obtaining satisfactory financial security, which must be presented to the Township within 90 days. The resolution or letter of contingent approval shall expire and be deemed to be revoked if the financial security agreement is not executed within 90 days unless a written extension is granted by the governing body.
C. 
Without limitation as to the types of financial security which the Township may approve, which approval shall not be unreasonably withheld, federal or commonwealth chartered lending institution irrevocable letters of credit and restrictive or escrow accounts in such lending institutions shall be deemed acceptable financial security for the purposes of this section. Such financial security shall be posted with a bonding company or federal or commonwealth chartered lending institution chosen by the party posting the financial security, provided that said bonding company or lending institution is authorized to conduct such business within the commonwealth. Such security shall provide for, and secure to the public, the completion of any improvements fixed in the formal action or accompanying agreement for completion of such improvements.
D. 
Amount of financial security. The amount of financial security shall be equal to 110% of the estimated cost of the required improvements for which financial security is to be posted. The cost of the required improvements shall be estimated as of 90 days following the date scheduled for the completion of said improvements. Annually, the municipality may adjust the amount of the financial security by comparing the actual cost of the improvements which have been completed and the estimated cost for the completion of the remaining improvements as of the expiration of the 90th day after either the original date scheduled for completion or rescheduled date of completion. Subsequent to said adjustment, the municipality may require the developer to post additional security in order to assure that the financial security equals 110%.
E. 
Basis for establishing amount of security. If the party posting the financial security requires more than one year from the date of posting of the financial security to complete the required improvements, the amount of financial security may be increased by an additional 10% for each one-year period beyond the first anniversary date from posting of financial security or to an amount not exceeding 110% of the cost of completing the required improvements as reestablished on or about the expiration of the preceding one-year period by using the above bidding procedure or as established by the Township Engineer. In the case where development is projected over a period of years, Council (or the planning agency) may authorize submission of final plans by section or stages of development, subject to such requirements or guaranties as to improvements in future sections or stages of development as it finds essential for the protection of any finally approved section of the subdivision or land development.
F. 
Dispute over amount of financial security. Whenever a dispute may arise between an applicant or developer and the Township in that neither party can reach an accord or the amount of financial security to be posted, the procedures set forth in Section 509(g) of the Pennsylvania Municipalities Planning Code[2] shall be employed.
[2]
Editor's Note: See 53 P.S. § 10509(g).
G. 
Contracts. As a condition of final plan approval for all subdivisions or land developments, the applicant or developer shall enter into a written agreement with the Township (to be recorded in the office of Recorder of Deeds of Montgomery County) in a manner and form approved by the Township Solicitor, where they shall agree to:
(1) 
Construct or cause to be constructed, at their own expense, all streets, curbs, sidewalks, fire hydrants, streetlights, drainage facilities, street signs, monuments, capped sewers, parks and other improvements shown on said final plan when required to do so by the Township Council in accordance with the final plans, as finally approved, and in strict accordance with the standards and specifications of the Township.
(2) 
Maintain, at their own cost, said streets, curbs, sidewalks, drainage facilities, street signs, parks, monuments, fire hydrants, streetlighting, capped sewers and other improvements, until the same are accepted by the Township for public use, and for a period of 18 months thereafter, to repair and reconstruct the same or any part of one of them when such repair or reconstruction shall be specified by the Township Council as necessary by reason of faulty construction, workmanship or materials and at or before acceptance of such improvements by the Township.
(3) 
Install or cause to be installed, at their own expense and without any cost to the Township for any part of such installation, streetlighting facilities on all streets within and abutting the subdivision or land development, as they appear on the approved final plan.
(4) 
Obtain the easements and releases required when any street, drainage facility or other improvement wherein a subdivision abuts or traverses lands of persons other than the person holding legal title to the lands of the subdivision, at his own cost, and obtain from the owner of lands so abutted or traversed full releases from all damages which may change in grade, construction or otherwise of the street, drainage facility or other improvement, and such releases shall inure to the benefit not only of the owner of the subdivision, but to the Township as well.
(5) 
Promptly reimburse to the Township reasonable attorneys' and engineers' fees in accordance with this chapter.
(6) 
Construct or cause to be constructed, at their expense, road improvements along the frontage of the tract in accordance with this chapter.
(7) 
Additional conditions as may be determined to be necessary by the Township Solicitor.
A. 
A partial completion and release of financial security.
(1) 
As the work of installing the required improvements proceeds, the party posting the financial security may request the Township Council to release or authorize the release, from time to time, of portions of the financial security.
(2) 
Any such request shall be in writing, addressed to Township Engineer. The Township Engineer shall certify, in writing, to Council that such portion of the work upon the improvements has been completed in accordance with the approved plans.
(3) 
Upon such certification, Council may authorize release by the bonding company or lending institution of an amount as estimated by the Township Engineer that fairly represents the value of the improvements completed.
(4) 
Township Council may, prior to final release at the time of completion and certification by its Engineer, require retention of 10% of the estimated cost of the aforesaid improvements for purposes of securing the maintenance bond on said improvements.
(5) 
If the required financial security of 100 plus 10% is secured in separate accounts and the specified 10% remains secured for the life of the security agreement and the construction period or until dedication, then the 10% specified above shall not be retained from the requested partial release.
B. 
Completion of improvements and release from financial security.
(1) 
When the developer has completed all of the necessary and appropriate improvements, the developer shall notify the Township, in writing, by certified or registered mail, of the completion of the aforesaid improvements and shall send a copy thereof to the Township Engineer.
(2) 
The Township Council shall, within 10 days after receipt of such notice, direct and authorize the Township Engineer to inspect all of the aforesaid improvements. The Township Engineer shall, thereupon, file a report, in writing, with Council and shall promptly mail a copy of the same to the developer, by certified or registered mail. The report by the Township Engineer shall be detailed and shall indicate approval or rejection of said improvements, either in whole or in part, and if said improvements or any portion thereof shall not be approved or shall be rejected by the Township Engineer, said report shall contain a statement of reasons for such nonapproval or rejection.
(3) 
The Township Council shall notify the developer, in writing, by certified or registered mail, of the action of said Township Council within relation thereto.
(4) 
If any portion of said improvements shall not be approved, or shall be rejected by the Township Council, the developer shall proceed to complete the same and, upon completion, the same procedure or notification, as outlined herein, shall be followed.
(5) 
Upon satisfactory completion of all the necessary and appropriate improvements as approved by the Township Engineer and receipt by Council of the appropriate letter of certification of completion of said improvements, Council shall release or authorize to be released the balance of the financial security, minus the 15% as specified above. The 15% shall be retained until such time as the developer establishes additional financial security to ensure the structural integrity and functioning of the specified improvements as specified in § 198-55 herein.
A. 
Where Council accepts dedication of all or some of the required improvements following completion, Council shall require the posting of financial security as a maintenance guaranty to secure the structural integrity of said improvements, as well as the functioning of said improvements, in accordance with the design and specifications as depicted on the final plan for a term not to exceed 18 months from the date of acceptance of dedication. Said financial security shall be of the same type as otherwise required in this section with regard to installation of such improvements, and the amount of the financial security shall not exceed 15% of the actual cost of installation of said improvements.
B. 
To secure release from the maintenance guaranty and financial security, the developer shall notify Township Council and Township Engineer by certified or registered mail 90 days or as otherwise specified in the guaranty prior to the expiration date of said maintenance guaranty and request an inspection and written report by the Township Engineer as to the structural integrity and functioning of the specified improvements.
C. 
Upon receipt of said report and approval of the Engineer of the structural integrity and functioning of said improvements, Township Council shall release or authorize release of the maintenance guaranty financial security.
D. 
If the specified improvements are not found acceptable to the Township Engineer, the developer shall correct the same to the satisfaction of the Township Engineer and Council before the maintenance guaranty financial security is released.
In the event that any required improvements have not been installed as provided in this article or in accord with the approved final plan, Council is hereby granted the power to enforce any corporate bond or other security by appropriate legal and equitable remedies. If proceeds of such bond or other security are insufficient to pay the cost of installing or making repairs or corrections to all the improvements covered by said security, the Council may, at its option, install part of such improvements in all or part of the subdivision or land development and may institute appropriate legal or equitable action to recover the monies necessary to complete the remainder of improvements. All of the proceeds, whether resulting from the security or from any legal or equitable action brought against the developer, or both, shall be used for the installation of the improvements covered by such security and for any expenses incurred by the Township.