Hereafter all streets and roads proposed for dedication for public use
and maintenance within the corporate limits of Middle Smithfield Township
shall conform to the following general construction standards and requirements:
A.
Application. The construction standards and requirements
contained in this article are intended as the minimum for the preservation
of the environment and promotion of the public health, safety and general
welfare and shall be applied as such by Middle Smithfield Township in reviewing,
evaluating and inspecting the construction of all streets and roads intended
for dedication to the Township for public use and maintenance.
B.
Other ordinances and regulations.
(1)
Whenever other Township ordinances and/or regulations
impose more restrictive standards and/or requirements than those contained
herein, such other ordinances and/or regulations shall be observed; otherwise,
the standards and requirements of this chapter shall apply.
(2)
Where there are no applicable Township standards or requirements,
the streets and roads shall be constructed in accordance with standards and
requirements furnished by the Township Engineer and/or the Township Planning
Commission consultant, the Pennsylvania Department of Transportation, the
Pennsylvania Department of Environmental Protection or other applicable agencies.
C.
Modifications. Middle Smithfield Township may, subject
to appropriate conditions, modify the construction standards and requirements
as follows to preserve the environment and to protect the public health, safety
and general welfare:
A.
Clearing and grubbing. The street or road right-of-way
shall be cleared and grubbed to the extent shown on the approved cross sections
as follows:
(1)
All tree stumps, roots and other material deemed unsuitable
shall be removed from the grading area.
(2)
All branches of trees which extend over the roadway shall
be trimmed to attain a clear height of 20 feet above the cartway.
(3)
Within the areas where excavation is to be made, the
ground shall be cleared of all living and/or dead trees, stumps, brush and
other objectionable material. All embedded stumps or root mats shall be removed
to a depth of not less than 12 inches below the subgrade or slope surfaces.
(4)
Within areas where embankment is to be made five feet
or more in depth, trees and stumps shall be cut off as close to the ground
as is practicable, but not to exceed six inches above the ground surface.
Near the toe of embankment slopes, no stumps or trees shall extend above the
existing ground level.
(5)
Where an embankment is less than five feet in depth,
unless otherwise shown on the drawings or field conditions warrant special
treatment, all trees, stumps, roots, brush, matted roots, debris, sod and
vegetable matter within 10 feet of the edge of the pavement shall be removed
and grubbed to a depth of not less than eight inches below the existing ground
surface.
(6)
Voids created by the removal of stumps and roots shall
be backfilled and thoroughly compacted.
(7)
Rocks and/or boulders shall be removed to a minimum of
six inches below the finished subgrade.
B.
Excavation. All cuts shall be excavated to the extent
of the approved cross sections as follows:
(1)
Slopes shall be trimmed neatly to the lines and rate
of slope indicated on the original or revised drawings and/or cross sections
and the work left in a neat and acceptable condition. Slopes in cuts may be
varied during construction, according to the type of material encountered,
in order to obtain satisfactory stability.
(a)
All drilling and blasting shall be performed in a manner
to complete the excavation to the required lines to produce the least disturbance
to the material to be left in place.
(b)
Blasting shall be performed by a fully insured and licensed
contractor and shall be at the entire risk and responsibility of the applicant
and/or the contractor.
(2)
The excavated material shall be removed by a method which
will permit the designed or revised slope lines to be neatly and acceptably
trimmed to meet the existing conditions.
C.
Embankments. All fills shall be constructed to the lines
shown on the approved cross sections as follows:
(1)
The embankment foundation area shall be cleared and grubbed in accordance with Subsection A above.
(2)
Existing depression in embankment areas such as gullies
and old stream channels shall be backfilled to the adjacent ground elevation
in the same manner as specified for the foundation of embankments.
(3)
All material placed in embankments shall be reasonably
free of organic material and any other objectionable material considered unsuitable
for use in embankment construction.
(4)
Frozen material shall not be placed in embankments and
embankment material shall not be placed on material frozen to a depth of three
inches or more. If during construction the top of the embankment freezes to
a depth of three inches or more, the frozen material shall be removed before
additional material is placed.
(5)
Wet material or material containing moisture in excess
of that percentage which will ensure satisfactory compaction shall not be
placed in embankments, and embankment material shall not be placed on material
that has become unstable due to excessive moisture.
(6)
Dry material or material containing insufficient moisture
to obtain satisfactory compaction shall be moistened before compaction.
(7)
All embankment material, other than rock for wet areas as specified in § 162-18R(5) shall be placed in uniform horizontal layers of not more than a loose eight-inch depth for the full width of the cross section. Compaction will be determined based on nonmovement of the material under the compaction equipment.
(8)
Embankment material placed in areas inaccessible to the
compaction equipment shall be placed in uniform loose layers not exceeding
four inches in depth and compacted by means of mechanical tampers.
(9)
Rock shall, in general, be placed to form the base of
embankments for the full width of the cross section as follows:
(a)
Rock shall be placed in uniform loose layers not exceeding
in depth the approximate average size of the larger rock, but limited to a
maximum depth of 36 inches. Oversize rock shall be reduced in size until it
can be readily incorporated in a thirty-six-inch layer.
(b)
Rock shall not be dumped in final position but shall
be distributed by blading or dozing in a manner that will ensure proper placement
in the embankment so that voids, pockets and bridging will be reduced to a
minimum.
(c)
The top layer of a rock embankment shall be limited to
a maximum depth of 12 inches with all voids filled with smaller pieces, spalls
or granular material.
(d)
Before rock is placed on compacted embankment constructed
of other material, the top of the embankment shall be sloped from the center
line to the sides at a rate of approximately one inch to the foot and shall
be thoroughly compacted.
(10)
During construction, the top layer of compacted embankments
shall be kept shaped and drained at all times.
(11)
Slopes shall be neatly trimmed to the lines shown on
the drawings or as directed, and the finished work shall be left in a neat
and acceptable condition.
D.
Special rolling. This work shall consist of special rolling
of embankment or subgrade, as deemed necessary and as specified or directed
by the Township in accordance with the following specifications and in areas
specified by the Township.
(1)
Approved pneumatic-tired equipment shall be used for
special rolling and shall be such that the load may be varied from 30 to 50
tons.
(2)
When the special rolling of any area shows that area
to be unstable, such an area shall be brought to satisfactory stability by
additional compaction or by removal of unsuitable materials, replacement with
suitable material and compaction.
(3)
The roller shall be operated in a systematic manner so
that the number of passes over all areas can be readily determined and recorded.
The roller shall normally be operated at a speed of not less than 2 1/2 miles
per hour.
(4)
Special rolling shall be performed only in the presence
of the Township Roadmaster, the Township Engineer and/or the Township Planning
Commission consultant whose duty it will be to approve or disapprove the stability
of the embankment and to recommend corrective measures.
E.
Cross drainage and culvert pipe. Construction standards
for all cross drainage and culvert pipe shall be as follows:
(1)
Pipe trenches shall have a minimum width of twice the
outside diameter of the pipe.
(2)
Pipe trenches shall be excavated through natural ground,
or where pipe structures are to be placed under embankment, the contractor
shall, unless otherwise directed by the Township, complete the construction
of the embankment to a minimum elevation of one foot above the elevation of
the top of the pipe before excavating the pipe trench. Where running water
is encountered and cannot be diverted, a temporary pipe shall be placed in
the trench prior to constructing the embankment.
(3)
When rock or hard shale is encountered, it shall be excavated
below the bottom of the pipe a minimum of eight inches and filled with suitably
compacted material.
(4)
When the material encountered is unstable, it shall be
entirely removed under the pipe for the full width of the trench or as otherwise
required for the particular condition and replaced with suitable material
mechanically tamped in four-inch layers to a satisfactory density.
(5)
When indicated on the drawings or directed by the Township,
the pipe shall be laid in a cradle constructed of Class B (5,000 pound) concrete
and reinforced when directed.
(6)
All pipe shall be laid carefully, bells upgrade, spigot
ends fully entered into adjacent hub and true to line and grade.
(a)
All pipe shall be laid with cemented joints, except the
interlocking style and pipe joined with bands.
(b)
Before succeeding sections of pipe are placed, the lower
half of the joint shall be plastered with approved cement mortar to bring
the inner surface of the abutting pipe flush and even. The cement mortar shall
be composed of one part of cement and two parts of sand mixed with a sufficient
quantity of water to form a plastic mortar.
(c)
The outside of the joint shall be overfilled with cement
mortar to form a bead around the pipe.
(d)
The inside of the pipe shall be wiped clean and finished
smoothly.
(7)
When pipes are protected by endwalls or connected with
drainage structures, the exposed ends of the pipe shall be placed or cut off
flush with the face of the structure.
(8)
Where pipe culverts are constructed in conjunction with
existing drainage structures, provision shall be made for satisfactory connections.
(9)
After a pipe is laid, the trench shall be backfilled
in four-inch layers with suitable material and thoroughly compacted under
the haunches and along the sides with mechanical tampers or other approved
methods.
F.
Subgrade drains. Subgrade drains shall consist of a trench
under the base filled with coarse aggregate and extending through the shoulder
area and beyond to a suitable outlet and shall be constructed as follows:
(1)
The trenches for these drains shall have a minimum width
of 15 inches and a minimum depth of six inches under the base course.
(2)
The bottom of the trench shall have a minimum slope of
1/4 inch per foot under the base and 1/2 inch per foot under the shoulder
area.
(3)
The trenches shall be placed at right angles or at a
skew with the roadway center line as directed.
(4)
The trench under the base course shall be filled with
aggregate to the elevation of the subgrade and shall extend the full width
of the base.
(5)
The outlet ends of all subgrade drains shall be marked
with appropriate stakes and must be kept open at all times during construction
and until final acceptance.
(6)
Subgrade drains shall be constructed as indicated in
Figure C-6[1] at locations noted on the drawings and where deemed necessary
by the Township.
[1]
Editor's Note: Figure C-6 is included at the end of this chapter.
G.
Pipe underdrains. Pipe underdrains shall consist of a
trench in which a pipe of the diameter specified shall be laid and the trench
filled with Type I or Type II backfill.
(1)
Type I backfill shall consist of coarse aggregate to
a depth indicated and the top of the trench filled with suitable soil.
(2)
Type II backfill shall consist of coarse aggregate covered
with fine aggregate to the depth indicated and the top of the trench filled
with suitable soil.
(3)
The pipe underdrain shall be placed after rough grading
is completed, but before the base course is placed, except as otherwise directed
by the Township.
(4)
The trench shall be excavated carefully, true to lines
and grades and to a minimum depth of 30 inches unless otherwise indicated
on the drawings, and the bottom of the trench shall be 15 inches wide.
(5)
A satisfactory outlet for pipe underdrain shall be provided.
(6)
Type I backfill shall be placed where trench excavation
is in rock or shale or where specified or directed by the Township.
(7)
Type II backfill shall be placed where trench excavation
is in soil or where specified or directed by the Township.
(8)
Where underdrains are constructed to join with existing
drainage structures, provision shall be made for satisfactory connections
as required.
(9)
Pipe underdrains shall be constructed as indicated in
Figure C-5[2] except where a special design is indicated or specified by the
Township.
[2]
Editor's Note: Figure C-5 is included at the end of this chapter.
H.
Pipe underdrain outlets. Pipe underdrain outlets shall
be pipe of the diameter specified, laid in a trench and backfilled with soil
and the outlet ends protected with concrete endwalls. (See Figure C-6.[3])
(1)
Outlet pipe shall be first quality plain cement concrete
pipe, unperforated corrugated metal pipe or equal.
(2)
The joints of the concrete pipe shall be filled with
mortar composed of one part cement and two parts sand.
(3)
Pipe for outlets shall be of the same material as the
pipe of the adjoining underdrain.
(4)
When outlets are constructed to join existing drainage
structures, provisions shall be made for satisfactory outlet connections.
[3]
Editor's Note: Figure C-6 is included at the end of this chapter.
I.
Subgrade. Subgrade shall consist of the preparation of
the top surface of the roadbed to accommodate the placement of the base and
shoulders in accordance with the following standards and in close conformity
to the lines, grades and widths shown on the drawings and cross sections.
(1)
The design and construction of the roadbed shall take
cognizance of the supporting capabilities of the subgrade, with particular
attention to those soils which are subject to frost heave.
(2)
Unsuitable soils shall be removed and replaced, drained
or otherwise stabilized to provide adequate support for the roadbed and anticipated
loads.
(3)
The graded roadbed shall be formed to the established
subgrade elevation and cross section and thoroughly compacted.
(4)
The subgrade shall be provided for the full width of
the base course and shoulder area.
(5)
Compaction will be determined based on nonmovement of
the material under compaction equipment.
(6)
Any subgrade which displays pronounced elasticity or
deformation under compaction equipment shall not be allowed. When stability
cannot be obtained, the material in the area shall be excavated to a depth
so that, when replaced and recompacted, the subgrade will have the required
stability.
(7)
The subgrade shall be protected and maintained at all
times. Any unsatisfactory areas shall be reshaped and recompacted prior to
the placement of the base and shoulder material.
J.
Engineering stakeout of roadway. A stakeout of the proposed
roadway shall be set to guide the contractor and to give the Township a method
of checking lines and grades to assure the road is built in conformity with
the drawings and cross sections. This stakeout for the different operations
shall be as follows:
(1)
Stakes for clearing and grubbing shall be set where side
slopes of cut or fill meet the natural ground, making sure all the slopes,
including the rounding at the top of cuts and ditches at the bottom of fills,
are included.
(2)
Stakes for grading operations shall be set to show proposed
cuts and fills prior to starting the grading operation.
(3)
If it is deemed necessary or desirable by the Township,
a final layout of the roadway shall be done when the paving is completed by
marking on the pavement at even fifty-foot stations the center line as designated
on the drawings. Stations shall be marked using PK nails and orange patch
flagging with the station numbers either painted on the pavement or marked
on offset stakes.
K.
Crushed aggregate base course. The base course shall
consist of construction of a layer or layers of crushed aggregate or other
approved material on a prepared subgrade in accordance with the following
standards and in close conformity to the lines, grades, widths and depths
shown on the approved drawings and cross sections.
(1)
Base material shall be placed in layers of uniform depth
not exceeding eight inches in compacted depth.
(2)
Base material shall not be placed on soft, muddy or frozen
areas, nor until all irregularities in the prepared subgrade, including soft
areas in the foundation, have been satisfactorily corrected.
(3)
Unstable base conditions which develop ahead of the paving
operation shall be satisfactorily corrected by scarifying, reshaping and recompacting
or replacement as required.
(4)
When required by the Township, crown templates, string
lines and straight edges shall be furnished and used to control the finished
elevations and smoothness of the base course.
(5)
The base material shall be maintained in a moist condition
during hauling, placing and compacting.
(6)
The base material shall be deposited on the prepared
subgrade by means of mechanical spreaders in a manner which will not cause
segregation.
(7)
In the event that the base material fails, after placement,
to compact to sufficient density, moisture may be added to obtain compaction.
If compaction is not obtained, the material shall be remixed, reconstructed
or removed and replaced.
(8)
The uniformly spread material shall be compacted by means
of a ten-ton roller or its equivalent. Compaction will be determined based
on nonmovement of the material under the compaction equipment.
(a)
When constructed in part width, the extension of the
base course shall not proceed to its full width until the existing edge of
the base is trimmed and all foreign and deleterious material is removed from
the remaining prepared subgrade area.
L.
Bituminous concrete base course. This work shall consist
of constructing one or more layers of hot-mixed, hot-laid bituminous concrete
base course in accordance with the Pennsylvania Department of Transportation's
specifications, Form 408 and/or any amendments thereto, and in close conformity
to the lines, grades, widths and depths shown on the drawings and cross sections.
M.
Alternate types of base course. Any base course proposed
but not covered in this chapter shall be constructed in accordance with the
Pennsylvania Department of Transportation's specifications, Form 408, or by
special specifications approved at the same time as the street or road plans.
N.
ID-2 bituminous paving. This work shall consist of constructing
one or more layers of hot-mixed hot-laid asphalt concrete on a prepared base
in accordance with the Pennsylvania Department of Transportation's specifications,
Form 408 and/or any amendments thereto, and in close conformity to the lines,
grades, widths and depths shown on the approved drawings. A minimum depth
of ID-2 bituminous paving shall be 2 1/2 inches.[4]
[4]
Editor's Note: Original Section 4.215, entitled "CP-2 Bituminous Paving,"
which immediately followed this subsection, was repealed 8-6-1997 by Ord.
No. 82.
O.
Alternate types of pavement. Any pavement proposed but
not covered in this chapter shall be constructed in accordance with the Pennsylvania
Department of Transportation's specifications, Form 408, or by special specifications
approved at the same time as the street or road plans.