The City or its agent(s) shall perform routine inspections during the construction of the stormwater management facilities and periodically thereafter to ensure compliance with the approved plans. Any portion of the stormwater management facilities which does not comply with the approved plan will be promptly corrected after receiving notice from the City. The notice shall set forth the nature of the deficiency and the time under which such deficiencies shall be completed.
A. 
After commencement of initial site operations, regular inspection shall be made at the following stages of construction:
(1) 
Upon completion of stripping, stockpiling and installation of the temporary sediment control and drainage facilities.
(2) 
Excavation of the facility to subbase and trenches for enclosed storm drainage pipe, concrete structures and catch basins.
(3) 
During placement of structural fill, trench backfill and embankment construction.
(4) 
Upon completion of final grading, fencing and establishment of permanent stabilization.
B. 
A final inspection shall be conducted by the Code Enforcement Officer upon completion of the stormwater management facility to determine if the completed work is constructed in accordance with the approved plan and this chapter. The Code Enforcement Officer may have the City Engineer jointly conduct an inspection.
C. 
An as-built drawing certified by the developer and his engineer is required to certify that the facility has been constructed as shown on the as-built plans and meets the approved plans and specifications.
D. 
The City shall provide the developer with written notification of the results of the final inspection.
E. 
If, as a result of the final inspection, the facility does not comply with the approved plans and the developer fails to correct any and all deficiencies within 30 days of written notification by the City, the City shall utilize the posted bond moneys or securities and have the facility constructed according to the plans.
A. 
Maintenance shall be ensured through inspection of all infiltration systems, retention or detention structures or other approved stormwater management facilities by the City or its Engineer. Inspection shall occur during its first year of operation and periodically thereafter at the discretion of the City.
B. 
If, after an inspection by the City or its Engineer, the condition of a stormwater management facility presents an immediate danger to the public health or safety because of an unsafe condition or improper maintenance, the developer shall be notified, in writing, of the condition and granted no more than 30 days to correct the problem.