The municipality may include all costs incurred in the review fee charged to an applicant. The review fee may include, but not be limited to, costs for the following:
A. 
Administrative/clerical processing.
B. 
Review of the SWM site plan.
C. 
Attendance at meetings.
D. 
Inspections.
For SWM site plans that involve subdivision and land development, the applicant shall provide a financial guarantee to the municipality for the timely installation and proper construction of all stormwater management controls as required by the approved SWM site plan and this chapter. The security shall be in the form of cash, certified check or a letter of irrevocable credit naming the Township as beneficiary, be for a term of 18 months, and be in an amount equal to 110% of the actual cost of the improvements and facilities so dedicated in accordance with the provisions of Sections 509, 510, and 511 of the Pennsylvania Municipalities Planning Code.[1]
[1]
Editor's Note: See 53 P.S. §§ 10509, 10510, and 10511, respectively.
A. 
When stormwater management facilities in the development have been completed in accordance with the final approved plan, such improvements shall be deemed private until such time as they have been offered for dedication to the Township and accepted by separate ordinance or resolution or until they have been condemned for use as a public facility.
B. 
Prior to acceptance of any improvements or facilities, the Township Engineer shall inspect them in accordance with the provisions of this chapter to ensure they are constructed in accordance with the approved plan and are functioning properly. In the case of any stormwater control facility, it must be free of sediment and debris.
C. 
The developer shall submit as-built plans in accordance with the provisions of this chapter for all facilities proposed for dedication.
D. 
Prior to acceptance of any improvements or facilities, the applicant shall provide financial security to secure the structural integrity and functioning of the improvements. The security shall be in the form of cash, certified check or other negotiable securities acceptable to the Township, be for a term of 18 months, and be in an amount equal to 25% of the actual cost of the improvements and facilities so dedicated.