Prior to the inspection of any phase of the work, it shall be
the applicant's responsibility to provide sufficient line stakes and
grade stakes to ensure that a proper inspection may be made. These
horizontal and vertical control stakes must be laid out to conform
to the lines and grades shown on the approved definitive plan or any
approved amendment thereto.
The following inspections of the required improvements shall
be required by the Board:
A. Inspection No. 1: Excavation prior to subgrading. An inspection shall
be made of the work upon completion of all clearing, grubbing and
excavation and all work incidental thereto as may be required. No
fill shall have been placed at the time of this inspection.
B. Inspection No. 2: Subsurface grading and filling. An inspection shall
be made of the compacted fill as may be required to bring the roadways
to their proposed grades. The applicant shall notify the Board or
its agent as to the applicant's source of fill as soon as such information
is known so that it may be determined if samples and analysis are
required. The applicant is advised not to proceed with the filling
operation until such time as the Board or its agent notifies the applicant
that the proposed fill is acceptable. If the applicant proceeds with
the fill prior to such notice, the applicant does so at its own risk.
C. Inspection No. 3: Drainage facilities and utilities.
(1)
An inspection will be made of the completed drainage system.
At the same time or such other time as the work may be available,
an inspection will be made of the completed municipal services (without
backfill) as required by the definitive plan. The inspection of the
required municipal services will be made by the agency responsible
for the particular service. Each agency so involved will notify the
Board or its agent of the approval of such work.
(2)
Backfill of any portion of the municipal services shall not
be made until after receipt of notification of approval or acceptance
by the Board or its agent, or the agency responsible.
D. Inspection No. 4: Roadway foundation. An inspection will be made
of the compacted roadway foundation.
E. Inspection No. 5: Pavement surface course. An inspection will be made of the completed roadway pavement. Samples of the mix may be taken by the Board or its agent for the purposes of determining if the roadway specifications and pavement thickness meet the requirements of the approved roadway section as contained within §
358-2.54.
F. Inspection No. 6: Final. An inspection will be made of all work as
required on sidewalks, curbing, landscaping, seeding, side slopes,
monuments, bounds and cleanup.