Projects subject to review as in Article I, § 179-3, of this chapter shall comply with the requirements of §§ 179-37 and 179-38.
A. 
The design engineer shall prepare a maintenance plan for the stormwater management measures incorporated into the design of a major development.
B. 
The maintenance plan shall contain specific preventative maintenance tasks and schedules; cost estimates, including estimated cost of sediment, debris, or trash removal; and the name, address, and telephone number of the person or persons responsible for preventative and corrective maintenance (including replacement). The plan shall contain information on BMP location, design, ownership, maintenance tasks and frequencies, and other details as specified in Chapter 8 of the NJ BMP Manual, as well as the tasks specific to the type of BMP, as described in the applicable chapter containing design specifics.
C. 
If the maintenance plan identifies a person other than the property owner (for example, a developer, a public agency or homeowners' association) as having the responsibility for maintenance, the plan shall include documentation of such person's or entity's agreement to assume this responsibility, or of the owner's obligation to dedicate a stormwater management facility to such person under an applicable ordinance or regulation.
D. 
Responsibility for maintenance shall not be assigned or transferred to the owner or tenant of an individual property in a residential development or project, unless such owner or tenant owns or leases the entire residential development or project. The individual property owner may be assigned incidental tasks, such as weeding of a green infrastructure BMP, provided the individual agrees to assume these tasks; however, the individual cannot be legally responsible for all of the maintenance required.
E. 
If the party responsible for maintenance identified under Subsection C above is not a public agency, the maintenance plan and any future revisions based on Subsection G below shall be recorded upon the deed of record for each property on which the maintenance described in the maintenance plan must be undertaken.
F. 
Preventative and corrective maintenance shall be performed to maintain the functional parameters (storage volume, infiltration rates, inflow/outflow capacity, etc.) of the stormwater management measure, including, but not limited to, repairs or replacement to the structure; removal of sediment, debris, or trash; restoration of eroded areas; snow and ice removal; fence repair or replacement; restoration of vegetation; and repair or replacement of nonvegetated linings.
G. 
The party responsible for maintenance identified under Subsection C above shall perform all of the following requirements:
(1) 
Maintain a detailed log of all preventative and corrective maintenance for the structural stormwater management measures incorporated into the design of the development, including a record of all inspections and copies of all maintenance-related work orders;
(2) 
Evaluate the effectiveness of the maintenance plan at least once per year and adjust the plan and the deed as needed; and
(3) 
Retain and make available, upon request by any public entity with administrative, health, environmental, or safety authority over the site, the maintenance plan and the documentation required by Subsections F and G above.
H. 
The requirements of Subsections C and D do not apply to stormwater management facilities that are dedicated to and accepted by the municipality or another governmental agency, subject to all applicable municipal stormwater general permit conditions, as issued by the Department.
I. 
In the event that the stormwater management facility becomes a danger to public safety or public health, or if it is in need of maintenance or repair, the municipality shall so notify the responsible person in writing. Upon receipt of that notice, the responsible person shall have 14 days to effect maintenance and repair of the facility in a manner that is approved by the municipal engineer or his designee. The municipality, in its discretion, may extend the time allowed for effecting maintenance and repair for good cause. If the responsible person fails or refuses to perform such maintenance and repair, the municipality or county may immediately proceed to do so and shall bill the cost thereof to the responsible person. Nonpayment of such bill may result in a lien on the property.
Nothing in this chapter shall preclude the municipality in which the major development is located from requiring the posting of a performance or maintenance guarantee in accordance with N.J.S.A. 40:55D-53.
A. 
In accordance with the provisions of N.J.S.A. 40:55D-53(2)(b), the developer shall post with the municipality, upon the inspection and issuance of final approval of the following private site improvements by the Municipal Engineer, a maintenance guarantee in an amount not to exceed 15% of the cost of the installation of the following private site improvements: stormwater management basins, inflow and water quality structures within the basins, and the outflow pipes and structures of the stormwater management system, which cost shall be determined according to the method of calculation set forth in Section 15 of P.L. 1991, c. 256 (N.J.S.A. 40:55D-53.4).
B. 
The term of the maintenance guarantee shall be for a period not to exceed two years and shall automatically expire at the end of the established term.
C. 
The maintenance guarantee shall be made payable and deposited to Springfield Township and shall be in the form of cash, irrevocable letter of credit, certified check, or a surety bond in which the applicant shall be principal, the bond to be provided by an acceptable surety company licensed to do business in the State of New Jersey. Irrevocable letters of credit shall be accepted only pursuant to N.J.S.A. 40:55D-53.5. Maintenance bonds shall be in the standardize format established by the New Jersey Department of Community Affairs pursuant to the provisions of N.J.S.A. 40:55D-53a.