[Ord. No. 1358, 9/12/2022]
1. The Borough shall inspect all phases of the installation of the best
management practices (BMPs) and/or stormwater management (SWM) facilities
as deemed appropriate by the Borough.
2. During any stage of the work, if the Borough determines that the
BMPs and/or stormwater management facilities are not being installed
in accordance with the approved SWM site plan, the Borough shall revoke
any existing permits or other approvals and issue a cease-and-desist
order until a revised SWM site plan is submitted and approved, as
specified in this Part and until the deficiencies are corrected.
3. An inspection of all BMPs and/or stormwater management facilities
may be conducted by the Borough to confirm compliance with the approved
SWM site plan prior to the issuance of any occupancy permit.
[Ord. No. 1358, 9/12/2022]
1. The applicant and/or developer shall be responsible for providing
as-built plans of all SWM BMPs included in the approved SWM site plan.
The as-built plans and an explanation of any discrepancies with the
construction plans shall be submitted to the Borough.
2. The as-built submission shall include a certification of completion
signed by a qualified professional verifying that all permanent SWM
BMPs have been constructed according to the approved plans and specifications.
If any licensed qualified professionals contributed to the construction
plans, they must sign and seal the completion certificate.
3. The applicant and/or developer shall be responsible for providing
the latitude and longitude coordinates for all permanent SWM BMPs,
at the central location of each BMP.
4. After receipt of the completion certification by the Borough, the
Borough may conduct a final inspection.