[Amended 4-16-1984 by Ord. No. 1984-2; 11-6-2025 by Ord. No. 2025-08]
The backfilling of trenches shall be performed by the owner and/or contractor making the opening in the following manner and under the supervision of the Township Engineer or Public Works General Foreman. All excavations shall be completely backfilled by the permittee and shall be compacted by tamping or other suitable means in a manner prescribed by the Township Engineer and Public Works General Foreman. The trench shall be backfilled to six inches below the road surface with cinder, coal or other materials approved by the Township Engineer or Public Works General Foreman, which shall be placed in layers not exceeding six inches in depth and thoroughly compacted to a depth of six inches below the level of the street. Cold patch shall complete the backfilling to raise the surface to street level. After 30 days, the permittee shall remove the cold patch and backfill material to a depth of eight inches, fill with six inches of concrete and, after curing of said concrete, apply two inches of FABC to bring the roadway surface to its original grade.