No subdivision or site plan involving any street(s)
requiring additional right-of-way width as specified in the Master
Plan or Official Map or the street requirements of this chapter shall
be approved unless such additional right-of-way, either along one
or both sides of said street(s), as applicable, shall be deeded to
the City or other appropriate governmental agency.
Applications for amended site plan or subdivision
review shall be governed by the same requirements as all other applications
for subdivision or site plan approval.
The submission requirements and review process
for conditional use applications shall be the same as for a major
site plan, except as set forth below.
A. The Board shall grant or deny an application for conditional
use approval within 95 days of submission of a complete application
or within such further time as may be consented to by the applicant.
If relief is requested pursuant to N.J.S.A. 40:55D-70d, the Board
shall grant or deny within 120 days of submission of a complete application
or within such further time as may be consented to by the applicant.
B. The Board shall approve or deny a conditional use
application simultaneously with any accompanying subdivision and/or
site plan application. The longest time period for action by the Board,
whether it be for subdivision, conditional use or site plan approval,
shall apply. Whenever approval of a conditional use is requested by
the applicant, notice of the hearing on the application shall include
reference to the request for conditional use approval.
No application for development shall be deemed
complete unless the items, information and documentation listed in
the applicable checklist are submitted to the Board. If any required
item is not submitted, the applicant must request in writing a waiver
and state the reasons supporting each such request.