The Planning Board may not formally accept an
application for site plan approval unless the following conditions,
and other conditions specified elsewhere, have been complied with:
A. Site plan approval applications. Three copies of the
application form, to be provided by the Secretary of the Planning
Board, shall be completed and submitted.
B. Required number of maps and reports. Ten copies of
all maps and written reports shall be provided and submitted to the
Planning Board, plus one black- or blue-and-white print and one reverse
line sepia for submission to the County Planning Board.
C. Application fees. All application fees shall be paid
to the Secretary of the Planning Board.
D. Reports by other boards or agencies. Written reports by other boards or agencies as required by this Part
4 or requested by the Planning Board shall be received by the Planning Board, provided that such boards and/or agencies shall report within 30 days from the date of submission to said board or agency to review and comment on the same.
Amended site plan applications shall be filed
with the Secretary of the Planning Board and shall be considered at
the next regular meeting date of the Planning Board, provided that
the amended application is received no less than 10 working days before
said meeting date and said amendments are minor in nature as determined
by the Construction Official.
[Amended 7-19-1995 by Ord. No. 22-95]
A. All proposed improvements or development indicated
on the approved site plan map shall meet the requirements of all applicable
codes, ordinances and specifications of the Township, county, state
or federal governments and other agencies with jurisdiction over matters
pertaining to site development. Further, each site plan submitted
for review and approval by the Township shall comply with the requirements
of the Americans With Disabilities Act (ADA) and the requirements
of the State of New Jersey for handicap access and barrier-free design.
A notation certifying such compliance shall be placed on each site
plan.
B. The Construction Official and/or the Township Engineer
may authorize minor changes in the site plan caused by said conditions
and shall notify the Planning Board, in writing, of such changes.
The site plan, as approved by the Planning Board, shall be binding upon the applicant. Any changes from the approved plan shall require resubmission and reapproval by the Planning Board, except as provided in §
57-102B hereof. Site plan approval shall remain in effect for a period of three years from the date of approval. The Planning Board, upon request from the applicant, may, for good and sufficient reason, extend this time period. In the event that a particular facility is to be constructed in stages, a site plan for each particular stage shall be required for the issuance of each building permit.
In the event of a failure to comply with any
condition of site plan approval, the Construction Official, on his
own initiative, may revoke the construction permit or certificate
of occupancy, as the case may be, and seek to enjoin the violation,
or take such other steps as permitted by law.
The Construction Official may issue a temporary
certificate of occupancy in accordance with N.J.A.C. 5:23-2.23(g).