A soil erosion and sediment control plan at the same scale as the site plan, which meets the design requirements of this bylaw, shall be prepared and submitted to the Department of Public Works. The plan shall include, but not be limited to, the items listed below and, at a minimum, be designed to provide sufficient information to evaluate the effectiveness and acceptability of measures proposed for soil erosion and sediment control during construction to protect the environment, public welfare/health, and municipal facilities and utilities. The following information shall be detailed on the plan:
A.
Name, address and telephone number of owner, civil engineer and person responsible for implementation of the plan.
B.
Property lines.
C.
Location of all existing and proposed building and impervious surfaces.
D.
Location of all existing and proposed stormwater utilities, including structures, pipes, swales and detention basins.
E.
Soil erosion and sediment control provisions including explanation of technical basis used to select the practices chosen to minimize on-site erosion and prevent off-site sediment transport, including provisions to preserve topsoil and limit disturbance.
F.
Design details for both temporary and permanent erosion control structures.
G.
The Director may require any additional information or data deemed appropriate and/or may impose such conditions thereto as may be deemed necessary to ensure compliance with the provisions of this bylaw and regulations for the preservation of public health and safety.
H.
An attached vicinity map showing the location of the site in relationship to the surrounding area's watercourses, water bodies and other significant geographic features, and roads and other significant structures.
I.
Suitable contours for the existing and proposed topography.
J.
A clear and definite delineation of any areas of vegetation or tree disturbance. Note all vegetation that is to be removed and all vegetation that is to be saved.
K.
A clear and definite delineation of any wetlands, natural or artificial water storage detention areas, and existing drainage ditches on the site.
L.
A description of construction and stockpile and/or excess materials removed from the site expected to be stored on-site. The plan shall include a description of controls to reduce pollutants from these materials and other waste such as demolition debris, litter and sanitary wastes. The plan shall include storage practices to minimize exposure of the materials to stormwater. Discharging of refuse or other wastes to the MS4, including, but not limited to, discarded building materials, concrete truck wash out, chemicals, litter and sanitary wastes is strictly prohibited.
[Amended 2-17-2021 by Bylaw Amendment 21-866]
M.
A sequence of construction for the development site, including stripping and clearing; rough grading; construction of utilities, infrastructure, and buildings; and final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, areas of clearing, and establishment of permanent vegetation.