The applicant, in any activity requiring a permit, and which involves 10 or fewer single-family residences, after commencing initial operation, shall request inspection by the Township Engineer:
A.
Upon completion of stripping, the stockpiling of topsoil and disposal of all unsuitable material, but prior to beginning any other preparation of the ground.
B.
Upon completion of preparation of ground to receive fill, but prior to beginning any placement.
C.
Upon completion of rough grading, but prior to placing topsoil, permanent drainage or other site-development improvements and ground covers.
D.
Upon completion of final grading, permanent drainage and erosion control facilities, including established ground covers and planting, and all other work of the permit.