The Township places great value on the open exchange of ideas between the applicant and Township before the applicant invests considerable time and funds in the preparation and submittal of the applicant's preliminary and/or final subdivision and/or land development plan. The applicant is encouraged, but not required, to initiate the subdivision and/or land development process by completing the sketch plan process. The sketch plan shall be prepared in accordance with Article 5 and is a permissive and not a mandatory submission. The submission of the sketch plan enables East Hempfield Township to openly discuss the applicant's project and to make recommendations for the applicant to consider in preparing the formal submission. In accordance with §
265-4.3D(1)(a), an applicant who elects to take advantage of the sketch plan process will, at the applicant's option, have the right to seek a modification of the preliminary plan process and, if approved, forego the preliminary plan processing requirements. Again, the sketch plan process is encouraged in all situations, but is not mandatory; however, an applicant cannot request a modification of the preliminary plan process unless he has submitted a sketch plan. In accordance with Section 265-4.3.D.(1)(b), an applicant who obtains conditional use approval of its project shall also have the right, at the applicant's option, to seek a modification of the preliminary plan process if a site plan was included with the conditional use application, said site plan must have illustrated all salient features of a sketch plan (§
265-5.2). If approved, the applicant may forego the preliminary plan processing requirements.
A. General. All applicants for subdivision and/or land development are encouraged to submit a sketch plan to East Hempfield Township for review prior to submission of a formal application; however, submission of a sketch plan is not mandatory. Submission of a sketch plan does not constitute a formal subdivision or land development application.
B. Plan information. Sketch plan reviews are not required to be consistent with procedures of the PA MPC. Sketch plans prepared for review and discussion should include those items listed in §
265-5.2.
C. Submission, meeting, and consultant review. Submission of the sketch plan application to the Township shall consist of:
(1) Sketch plan. Sufficient paper copies of the sketch plan as determined by the Board of Supervisors, plus one additional copy if the subject tract is within one mile of a Township boundary and one additional copy if the subject tract abuts a state highway. In addition, two CD/DVDs with PDFs of all submitted documents shall be required.
(2) Supplemental data. Two paper copies of all reports, notifications and certifications that are not provided on the sketch plan.
(3) Zoning approval.
(a) If the sketch plan has been the subject of a zoning approval process (variance, special exception, and/or conditional use), this zoning approval process should be decided by the Board of Supervisors and/or the Zoning Hearing Board, as applicable, prior to submission of the sketch plan. A paper copy of all prior, relevant zoning decisions must be submitted with the sketch plan. A sketch plan may be submitted prior to final resolution of zoning approvals when the Township's recommendations on a sketch plan may influence the particular zoning approval to be sought by a plan's applicant.
(b) The applicant shall meet with the Township Zoning Officer prior to submitting the sketch plan. The Township Zoning Officer shall review the plan with the applicant and issue a letter identifying either that the proposed activity/plan appears to generally comply with the Township Zoning ordinance or that the proposed activity/plan does not appear to comply with the Township Zoning ordinance and that corrections will be made prior to submitting the sketch plan or that zoning approval will be sought in accordance with Subsection C(1)(a) above. Such letter, as issued by the Zoning Officer, shall be submitted with the sketch plan.
(4) Application form. One application form completely and correctly executed, with all information legible, and bearing all required signatures.
(5) Filing fee. A filing fee in accordance with East Hempfield Township's current fee schedule.
D. Meeting and consultant review.
(1) The applicant may schedule a review meeting with the Township Staff which may include the Township Manager, Assistant Manager, Director of Planning (or his designee), Zoning Officer, Township Engineer, other appropriate Township staff, and/or County Community Planner. The applicant shall be responsible for costs associated with this meeting.
(2) The Township Planning Commission, Township Engineer, and/or legal consultant may perform a written review of the sketch plan, at the applicant's sole cost and expense; however, such written review is required if, following the sketch plan, a final plan will be submitted in lieu of a preliminary plan. In such cases, the written review shall be provided to the applicant with copies to Township Staff, the Township Planning Commission, and the Lancaster County Planning Commission.
E. Review by Township Planning Commission.
(1) The Township Planning Commission shall review the sketch plan submission and, as applicable, the consultant reviews and advises the applicant how the proposed subdivision or land development may conform or fail to conform to the requirements and objectives of this chapter and other applicable plans and ordinances. The Township Planning Commission may then submit its written comments and recommendations to the applicant.
(2) If the applicant has requested a modification of the preliminary plan process as part of his sketch plan submission, the Township Planning Commission shall recommend approval or denial of the waiver/modification during its review of the sketch plan. The Planning Commission will not make recommendations on any other modification requests during the sketch plan process.
F. Review by Board of Supervisors.
(1) The applicant may, but need not, request further review of the sketch plan submission by the Board of Supervisors at a regularly scheduled meeting. The Board of Supervisors may provide written comments to the applicant. Said comments shall not be deemed to be an approval of any application or to vest any rights in the applicant.
(2) At this time, the Board of Supervisors shall also take note of the Township Planning Commission's recommendation for approval/denial of a modification of the preliminary plan process and may approve/deny such request as part of its review of the sketch plan. The Board of Supervisors does not approve, deny, or act on a sketch plan request and Board comments shall not be deemed to be an approval of any application or to vest any rights in the applicant.
G. Completion of the sketch plan process. After completion of the sketch plan process or conditional use process (if required by the Zoning ordinance), the applicant is allowed to do one of the following:
(1) Preliminary plan submission processed per §
265-4.3; followed by final plan submission, per §
265-4.4.
(2) Final plan submission, processed per §
265-4.4 if the Board of Supervisors approved the modification of the preliminary plan process.