This article sets forth the application requirements for obtaining approval of subdivision and land developments. The form of the various plans referred to in this article and the information required to be furnished with such plans shall be as specified in Article
IV.
The procedures set forth in this section shall apply as an alternative
to the guaranteeing of improvements through a letter of credit or
other financial security. An applicant whose improvement construction
plan is approved under this section is permitted to install all or
part of the improvements required by this chapter prior to final plan
submission.
A. Improvement construction plan application. After an applicant has
received official notification that the preliminary plan has been
approved and the required changes, if any, have been made, an application
may be processed for an improvement construction plan. The improvement
construction plan may be submitted in sections, each section covering
a reasonable portion of the entire proposed subdivision as shown on
the approved preliminary plan.
B. Application requirements. All improvement construction plan applications shall be made and processed in accordance with §§
119-24 and
119-25D through
K herein.
[Amended 2-19-2024 by Ord. No. 342-2024]
A developer shall file as-built plans of all street improvements,
stormwater management facilities, public water supply facilities,
public sewage disposal facilities and other public improvements at
the completion of construction and before any dedication for public
use. One paper set of as-built plans and one set in an electronic
format acceptable to the Township Engineer shall be filed with the
Township Secretary. The Township Engineer shall review and approve
the as-built plan. The Township shall not release of the financial
security until the as-built plan is submitted, reviewed and approved
by the Township Engineer and the Township Engineer has issued the
completion certificate.