[Amended 12-11-2013 by Ord. No. 409; 12-8-2021 by Ord. No. 466]
Within 30 days after completion and approval by the Township
of improvements as shown on the final plans, and before acceptance
of such improvements, the applicant shall submit to the Board of Supervisors
a final corrected copy of said plans. These plans shall be in electronic
format deemed acceptable by the Township. Hardcopy versions of as-built
plans shall also be submitted on twenty-two-inch by thirty-four-inch
or on twenty-four-inch by thirty-six-inch plan sheets. All as-built
plans shall indicate all actual dimensions, elevations, site grading,
and locations of all site improvements, including field changes. All
as-built plans shall also be certified by the applicant and by a registered
surveyor or engineer to be in accordance with actual construction.
Additionally, the location and elevations of all sewer laterals and
water services shall also be indicated. As-built plans shall be required
for all subdivisions with site improvements (road, storm sewer system,
sanitary sewer system, etc.) and all residential and nonresidential
land developments.
[Amended 2-23-2011 by Ord. No. 376]
A. When the developer has completed all of the necessary
and appropriate improvements and would request release of the improvement
bond, the developer shall notify the Township, in writing, by certified
or registered mail, of the completion of the aforesaid improvements
and shall send a copy thereof to the Township Engineer. The Township
Engineer shall inspect all of the aforesaid improvements and shall,
within 30 days, file a report, in writing, with the Township and shall
promptly mail a copy of the same to the developer by certified or
registered mail. Said report shall indicate approval or rejection
of said improvements, either in whole or in part, and if said improvements,
or any portion thereof, shall not be approved or shall be rejected
by the Township Engineer, said report shall contain a statement of
reasons for such nonapproval or rejection.
B. The Township shall notify the developer, within 15
days of receipt of the engineer's report, in writing, by certified
or registered mail, of the action of the Township with relation to
approval, nonapproval or rejection of improvements.
C. If any portion of said improvements shall not be approved
or shall be rejected by the Township, the developer shall proceed
to complete the same and, upon completion, the same procedure of notification
as outlined herein shall be followed.
D. The developer shall be responsible for maintenance
(including, but not limited to, snowplowing, repairs and maintenance,
etc.) of all improvements until such improvements are accepted for
dedication by the Township.