Observations shall be required before the start of construction, during installation of materials and structures, and upon the completion of all improvements. Before the initiation of construction, the developer shall arrange a pre-construction meeting with the Township Engineer and Township Roadmaster, or designee(s), so that an observation schedule can be coordinated within the construction schedule. The Township Engineer and Township Roadmaster, or designee(s), shall be notified five working days in advance of any intended date of construction. The provisions stated herein shall not be construed as mandating periodic inspections, and the undertaking of periodic observations shall not be construed as an acceptance of the work during construction or as a final observation of the construction. The Township, at the expense of the developer, reserves the right to require drawing details, shop drawings, and tests by approved testing facilities, to determine whether the improvement complies in all respects with the requirements of the Township.
A. Inspection of public improvements by Township. The portions of the construction listed herein shall be inspected as follows:
(1) Underground utilities. Inspection of utility installation shall be performed by the utility company or utility authority having jurisdiction. Inspection and testing of trench backfill, pipe/conduit installation, including service laterals, relays, meter pits, hand holes, transformer foundations, poles, guide wires, manholes, prior to backfilling.
(2) Concrete curb. Observation before installation of string line to show curb, grade and alignment. Constant and full-time inspection of material placement, including the submittal of all certified material delivery slips.
(3) Sidewalk. Constant and full-time inspection of material placement, including the submittal of all certified material delivery slips.
(4) Storm drainage easements. Observation of finish grade elevations, alignments and profiles of each storm drainage easement.
B. Soil erosion and sediment pollutant control. The developer may, without the need for inspection during construction, construct the erosion and sediment pollution control facilities. Upon completion of construction of the erosion and sediment pollution control facilities, Developer shall contact the Township Engineer and/or designee to inspect the same. Developer shall not proceed with construction of any other public improvement until such time as the erosion and sediment pollution control facilities have been inspected and approved in writing by the Township Engineer.
C. Clearing and grubbing. Developer may, after the erosion and sediment pollution control facilities have been inspected and approved by the Township Engineer thereof, and without the need for inspection, conduct the clearing and grubbing and other grading work within the development.
D. Sewage disposal system. Developer shall be solely responsible to ensure that the Township Engineer is notified at least five working days prior to commencement of the construction of said sewage disposal system and shall permit the Township Engineer, Township Roadmaster, or designee(s) to inspect construction of said sewage disposal system on a constant and full-time basis.
E. Stormwater management facilities. Developer shall permit the Township Engineer, Township Roadmaster, or designee(s), to inspect the stormwater management facilities on a constant and full-time basis during the construction of the stormwater management facilities. The stormwater management facilities shall include, but not be limited to, detention basins, retention basins, infiltration basins, ditches and ditch linings, swales and swale linings, storm sewers, culverts, inlets, manholes, end walls, and cross pipes. Developer shall be solely responsible to ensure that the Township Engineer is notified at least five working days prior to commencement of the construction of said stormwater management facilities.
F. Street. Street to be offered for dedication to the Township shall be inspected as follows:
(1) Clearing and grubbing. Developer may, without the need for inspection, conduct the clearing and grubbing of the roadways within the development.
(2) Rough grading (cut and fill stage). Developer shall have the right to employ an independent testing laboratory, approved by the Township Engineer, to conduct soil and soil compaction tests, and said laboratory shall present a certification to the Township which shall state the fill on every portion of the roadways is conducted in accordance with PennDOT Publication 408 Specifications, Section 210.3, latest edition. In the event developer employs such a laboratory and the Township receives said certifications, no inspection by the Township shall be required during the rough grading of the roadways (cut and fill stage). In the event developer does not employ an independent testing laboratory to test the fills on the roadways, the Township Engineer, Township Roadmaster, or designee(s), shall be present to inspect on a constant and full-time basis the entire construction of the rough trade of the roadways. Developer shall be solely responsible to ensure that the Township Engineer is notified at least five working days prior to commencement of the construction of rough grade of the roadways. Upon completion of the rough grading of the roadway and receipt by the Township of said certification of the independent laboratory (if developer employs same), developer shall, prior to proceeding with any further construction whatsoever on the roadways, notify the Township Engineer, Township Roadmaster, or designee(s), to permit the Township to inspect the completed rough grade (cut and fill) of the roadways.
(3) Subbase, base course and wearing course. In the event the Township approves the rough grading of the roadways, developer shall provide the Township Engineer, Township Roadmaster, or designee(s), at least five working days notice prior to construction of the subbase of the roadways. The Township Engineer, Township Roadmaster, or designee(s), shall conduct constant and full-time inspection of the roadways during construction of the subbase, base course and wearing course of the roadways.