A. Building.
(1) Alterations, repairs, and remodeling:
(a)
General: $45 per $1,000 for the first $50,000;
$35 per $1,000 for the next $150,000; $25 per $1,000 for the balance.
(c)
Residential roof: $35 per $1,000 of cost of
construction.
(d)
Commercial roof: $60 for the first $1,000 cost
of construction; $50 for every $1,000 thereafter.
(e)
Residential siding: $35 per $1,000 of cost of
construction.
(f)
Retaining walls:
[1]
Surface area greater than 550 square feet: $175.
[2]
Surface area of 550 square feet or less: $100.
(g)
Aboveground swimming pools (flat fee): $100.
(h)
Inground swimming pools: $250 for residential;
$500 for public.
(2) New residential, commercial and industrial:
(a)
For the following use groups: R-2, R-3, R-4,
R-5 and U: $0.038 per cubic foot.
(b)
For the following use groups: A-1, A-2, A-3,
A-4, A-5, B, E, F-1, F-2, H-1, H-2, I-1, I-2, I-3, M, R-1, S-1 and
S-2: $0.036 per cubic foot.
(c)
For large open volume building: $0.03 per cubic foot.
(3) Additions and expansion of floor area:
(a)
For the following use groups: R-2, R-3, R-4,
R-5 and U: $0.032 per cubic foot.
(b)
For the following use groups: A-1, A-2, A-3,
A-4, A-5, B, E, F-1, F-2, H-1, H-2, I-1, I-2, I-3, M, R-1, S-1 and
S-2: $0.034 per cubic foot.
(4) Demolition or removal of:
(a)
Residential accessory buildings: less than 2,000
square feet and less than 30 feet high: $125.
(b)
Residential buildings:
[1]
Two thousand square feet and less than 35 feet
high: $150.
[Amended 12-16-2021 by Ord. No. 2021-23]
[2]
Two thousand square feet to 5,000 square feet:
$200.
[3]
More than 5,000 square feet and less than 35
feet high: $250.
(c)
Commercial buildings: $500.
(d)
Lead abatement: $190 plus $28 for clearance
certificate.
[Amended 12-18-2018 by Ord. No. 2018-22]
(5) Signs:
(b)
For the first 100 square feet: $6 per square
foot.
[Amended 12-18-2018 by Ord. No. 2018-22]
(c)
For the next 400 square feet: $5 per square
foot.
[Amended 12-18-2018 by Ord. No. 2018-22]
(d)
Per square foot thereafter: $3.
(6) Certificates of occupancy:
(a)
Residential multiple certificate, per unit:
$75.
(b)
Residential certificate of occupancy (new):
$75.
(c)
Certificate of continued occupancy (all): $250.
(d)
Commercial certificate of occupancy: 15% of
the cost of the permit.
(g) Temporary certificates of occupancy ("TCO") may be issued for both
residential and commercial structures upon payment of a fee of $30
each and compliance with the requirements of the Construction Official.
(7) Additional fees:
(a)
Minimum building subcode fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(b)
Extending/updating expired permits: $75.
(c)
For anything not listed: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(d)
Application for variation:
[1]
Class I structures: $594.
[2]
Class II and Class III structures: $125.
(e)
Resubmission of an application for variation:
[1]
Class I structures: $250.
[2]
Class II and Class III structures: $75.
(g) A change of contractor review fee of $80 per discipline will be charged
for each change of contractor permit.
[Amended 12-16-2021 by Ord. No. 2021-23]
(i) Radon mitigation: $80.
[Amended 12-18-2018 by Ord. No. 2018-22]
B. Plumbing.
(1) Minimum plumbing fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(3) Water utility connection: $75.
[Amended 4-23-2020 by Ord. No. 2020-4]
(a) Water service (residential): $125.
(b) Water service (commercial): $ 150.
(4) Sewer utility connection: $75.
[Amended 4-23-2020 by Ord. No. 2020-4]
(a) Sewer connection (residential): $100.
(b) Sewer connection (commercial): $ 150.
(6) Air-conditioner unit: $75.
(12)
Gas-to-gas domestic furnace: $75.
[Amended 4-23-2020 by Ord. No. 2020-4]
(13)
Water conditioners/filter systems/refrigeration
unit: $65.
(14)
Active solar systems: $75.
(17)
Gas-to-gas steam boiler with electric permit:
$85.
(18)
Gas-to-gas hot-water boiler: $75.
[Amended 4-23-2020 by Ord. No. 2020-4]
(19)
Plumbing devices other than listed: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(23) Power
vent or instantaneous water heater: $100.
[Amended 4-23-2020 by Ord. No. 2020-4]
(24)
Floor, roof, and hub drains: $20.
(25)
Whirlpool/spa and hot tubs: $75.
(26)
Gas piping, each appliance: $20.
(27)
Extending/updating expired permits: $75.
(28) Vacuum
relief system: $75.
(29)
Refrigerator ice maker: $15.
(30)
Medical gas (per outlet): $15.
(31)
Additional fees:
(a)
Change of contractor review fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(32)
Air handler: $75.
[Amended 4-23-2020 by Ord. No. 2020-4]
(35)
Studor vent/air admittance device: $25.
(37) Mini-split
system with one wall unit: $75.
[Added 4-23-2020 by Ord. No. 2020-4]
(38) Extra
evaporator (mini-split): $25.
[Added 4-23-2020 by Ord. No. 2020-4]
C. Fire.
(1) Smoke and heat detectors (number of detectors); also
includes horn strobes, devices, exit and emergency lights:
(c)
One hundred and one to 200: $212.
(d)
Two hundred and one to 400: $550.
(e)
Four hundred and one to 1,000: $761.
(2) Sprinkler fees for wet and dry sprinkler heads (number
of heads):
(c)
One hundred and one to 200: $250.
(d)
Two hundred and one to 400: $750.
[Amended 12-16-2021 by Ord. No. 2021-23]
(e)
Four hundred and one to 1,000: $950.
[Amended 12-16-2021 by Ord. No. 2021-23]
(f)
Over 1,000: $1,100.
[Amended 12-16-2021 by Ord. No. 2021-23]
(3) Additional fees:
(a)
Each standpipe: $285.
[Amended 12-16-2021 by Ord. No. 2021-23]
(b)
Each incinerator: $400.
[Amended 12-16-2021 by Ord. No. 2021-23]
(c)
Each crematorium: $400.
[Amended 12-16-2021 by Ord. No. 2021-23]
(d)
Each gas or oil-fired appliance: $75.
(e)
Underground main and water tanks: $250.
(f)
Change of contractor review fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(4) Preengineered suppression systems:
(a)
Suppressions not listed: $150.
[Amended 12-16-2021 by Ord. No. 2021-23]
(e)
Dry chemical: $150.
[Amended 12-16-2021 by Ord. No. 2021-23]
(f)
Wet chemical: $150.
[Amended 12-16-2021 by Ord. No. 2021-23]
(g)
Kitchen exhaust system, residential: $70.
(h) Kitchen exhaust system, commercial: $150.
[Amended 12-16-2021 by Ord. No. 2021-23]
(5) Fuel tank installations: $75.
(6) Fuel tank abandonment: $125.
(7) Replacement heating unit: $75.
(8) Wood stove installation: $85.
(9) Extending/updating expired permits: $75.
(10)
Anything not listed: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(11)
Minimum fire subcode fee (commercial): $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(12)
Minimum fire subcode fee (residential): $75.
(13)
Fuel tank removals: $125.
(14)
Bollards (two-inspection process): $125.
[Added 12-16-2021 by Ord. No. 2021-23]
(15)
Solar panels: $125.
[Added 12-16-2021 by Ord. No. 2021-23]
(16)
Chimney liners: $125.
[Added 12-16-2021 by Ord. No. 2021-23]
D. Electrical.
(1) Switching, lighting, and receptacle outlet (devices
of less than one horsepower or one kilowatt included):
[Amended 12-15-2022 by Ord. No. 2022-012]
(2) Service panels, entrances, transfer switches and subpanels:
[Amended 12-18-2018 by Ord. No. 2018-22; 4-23-2020 by Ord. No. 2020-4]
(a)
For 100 amps or less: $100.
(b)
For 101 amps to 200 amps or less: $200.
[Amended 12-15-2022 by Ord. No. 2022-012]
(c)
For 201 to 400 amps or less: $300.
(d)
For 401 to 600 amps or less: $500.
(e)
For 601 to 1,000 amps or less: $625.
[Amended 12-15-2022 by Ord. No. 2022-012]
(f)
For 1,001 amps or more: $725.
[Amended 12-15-2022 by Ord. No. 2022-012]
(3) Transformers and generators:
[Amended 12-15-2022 by Ord. No. 2022-012]
(a)
From zero kilowatts to 10 kilowatts: $125.
(b)
From 11 kilowatts to 26 kilowatts: $150.
(c)
From 27 kilowatts to 45 kilowatts: $175.
(d) From 46 kilowatts to 112.5 kilowatts: $200.
(e)
Greater than 112.5 kilowatts: $500.
(4) Motors and electrical devices (control equipment,
heating, compressor, heat pump, air handler, strip heater, water heater,
dryer, oven, range, furnace, and dishwasher):
(a)
Zero horsepower to 10 horsepower: $75.
(b)
Eleven horsepower to 50 horsepower: $75.
(c)
Fifty-one horsepower to 100 horsepower: $115.
(d)
One hundred one horsepower to 150 horsepower: $150.
(e)
One hundred fifty-one horsepower to 200 horsepower: $300.
(f)
Two hundred one horsepower to 300 horsepower: $600.
(g)
Three hundred one horsepower or larger: $700.
(5) Bonding, pool/vault (outlets/receptacles): $75.
(6) Feeders:
(b)
Each additional 100 amperes: $65.
(7) Photovoltaic systems:
[Amended 12-15-2022 by Ord. No. 2022-012]
(b) Fifty-one to 100 kw: $425.
(c) Greater than 100 kw: $500.
(9) Extending/updating expired permits: $75.
(10)
Anything not listed: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(11)
Minimum electrical subcode fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(13)
Elevators (one to 10 floors): $250.
(14)
Residential elevator: $200.
(15)
Commercial ground-level HVAC: $100.
(16)
Commercial rooftop HVAC: $200.
(17)
Boiler and furnace: $75.
[Amended 12-18-2018 by Ord. No. 2018-22; 4-23-2020 by Ord. No. 2020-4]
(18)
Disconnect and automatic transfer switch (ATS) 100 amps or less:
$75.
[Amended 3-4-2021 by Ord. No. 2021-3]
(19)
Disconnect and automatic transfer switch (ATS) 101 to 200 amps:
$125.
[Amended 3-4-2021 by Ord. No. 2021-3]
(19.1) Disconnect and automatic transfer switch (ATS) more
than 200 amps: $150.
[Added 3-4-2021 by Ord.
No. 2021-3]
(20)
CSST (gas line) bonding: $75.
(21)
Additional fees:
(a)
Change of contractor review fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(23)
Aboveground pools: $125.
[Amended 12-15-2022 by Ord. No. 2022-012]
(24)
Car charging outlets:
(e)
Four hundred eighty volts: $125.
(f) Car charger 60 amp and higher: $125.
[Added 4-23-2020 by Ord. No. 2020-4]
(25)
New and replacement residential A/C: $75.
[Amended 4-23-2020 by Ord. No. 2020-4]
(a) Mini-split system with one wall unit: $75.
(b) Mini-split system additional wall unit: $25.
(27) X-ray
equipment: $100.
[Added 4-23-2020 by Ord. No. 2020-4]
(28) Annual
pool inspection: $150.
[Added 4-23-2020 by Ord. No. 2020-4; amended 12-15-2022 by Ord. No.
2022-012]
(29) Baseboard
heaters: $25.
[Added 12-16-2021 by Ord. No. 2021-23]
(30) Security
cameras: $75 for up to a total of 10 security cameras and an additional
fee of $75 for each 10 additional cameras thereafter.
[Added 12-16-2021 by Ord. No. 2021-23]
(31) Load
management:
[Added 12-15-2022 by Ord. No. 2022-012]
(a) Device up to 60 amps: $80.
(b) Device 61 to 100 amps: $100.
(32) Power
wall or solar storage system: $125.
[Added 12-15-2022 by Ord. No. 2022-012]
E. Elevators.
(1) The fee for a permit shall be $25 per unit, plus costs
charged by an on-site inspection agency as follows for witnessing
acceptance tests:
(a)
Traction and winding drum elevators:
[1]
One through 10 floors: $225.
(b)
Hydraulic elevators: $200.
(c)
Roped hydraulic elevators: $225.
(d)
Escalators and moving walks: $200.
(f)
Stairway chair lifts, inclined and vertical
wheelchair lifts and man lifts: $50.
(g)
Residential devices: $150.
(h)
Oil buffers (per oil buffer): $43.
(i)
Counterweight governor and safeties: $100.
(j)
Auxiliary power generator: $75.
(2) Semiannual routine inspections (fees per unit):
(a)
Traction and winding drum elevators:
[1]
One through 10 floors: $140.
(b)
Hydraulic elevators: $100.
(c)
Roped hydraulic elevators: $140.
(d)
Escalators and moving walks: $140.
(3) Annual inspections and witnessing of tests:
(a)
Traction and winding drum elevators:
[1]
One through 10 floors: $200.
(b)
Hydraulic elevators: $150.
(c)
Roped hydraulic elevators: $200.
(d)
Escalators and moving walks: $320.
(f)
Stairway chair lifts, inclined and vertical
wheelchair lifts and man lifts: $120.
(4) Additional yearly periodic inspection fees:
(a)
Oil buffers (per oil buffer): $43.
(b)
Counterweight governor and safeties: $100.
(c)
Auxiliary power generator: $75.
(5) Three- and five-year test/inspection fees:
(a)
Traction and winding drum elevators (five-year
inspection):
[1]
One through 10 floors: $340.
(b)
Hydraulic and roped hydraulic:
[1]
Three-year inspection: $250.
[2]
Five-year inspection: $150.
F. Mechanical.
(1) Minimum mechanical fee: $80.
[Amended 12-16-2021 by Ord. No. 2021-23]
(2) Gas-to-gas domestic furnace with electric permit: $100.
(5) Gas-to-gas hot water boiler with electric permit: $85.
(6) Devices other than those listed: $75.
(8) Gravity water heater: $75.
(9) Gas piping, each appliance: $20.
(11)
Change of contractor review fee: $80.
[Added 12-16-2021 by Ord. No. 2021-23]
[Added 12-15-2022 by Ord. No. 2022-012]
In addition to the fees specified above, for applications filed
electronically, the following fees are hereby established pursuant
to P.L. 2021, c. 70, subject to the standards set forth by the Commissioner
of Community Affairs:
A. Residential,
per individual permit application consisting of one or multiple disciplines:
$10.
B. Commercial,
per individual permit application consisting of one or multiple disciplines:
$15.
The Construction Official shall, with the advice
of the subcode officials, prepare and submit to the Township of Marlboro
biannually a report recommending a fee schedule based on the operating
expenses of the agency, and any other expenses of the municipality
fairly attributable to the enforcement of the State Uniform Construction
Code Act.
[Amended 3-24-1994 by Ord. No. 5-94; 12-10-2009 by Ord. No.
2009-35]
In order to provide training, certification
and technical support programs required by the Uniform Construction
Code Act and the regulations promulgated thereunder, the enforcing agency shall collect,
in addition to the fees specified above, a surcharge fee as per N.J.A.C.
5:23-4.19(b). Said surcharge fee shall be remitted to the Construction
Code Element, Division of Housing and Development, Department of Community
Affairs, on a quarterly basis for the fiscal quarters ending September
30, December 31, March 31 and June 30 and not later than one month
succeeding the end of the quarter for which it is due. The enforcing
agency shall report annually at the end of each fiscal year to the
Bureau of Housing Inspection, and not later than July 31, the total
amount of the surcharge fee collected.
[Amended 9-26-1996 by Ord. No. 29-96]
There shall be a reduction of 20% of the fee
being charged for any prototype construction permits. The fee shall
be calculated by calculating the actual permit fee required and then
subtracting therefrom a twenty-percent reduction to determine the
revised fee.
[Added 2-17-2011 by Ord. No. 2011-1; 3-2-2017 by Ord. No. 2017-5; 12-16-2021 by Ord. No. 2021-23; 12-15-2022 by Ord. No. 2022-012]
Charitable, philanthropic, fraternal, athletic, recreational and religious nonprofit organizations holding a tax-exempt status under the Federal Internal Revenue Code of 1954 [26 U.S.C. 501(c) or (d)] shall be eligible for a refund of 50% of the Uniform Construction Code ("UCC") fees set forth in §
125-3A(1), Alterations, repairs, and remodeling, paid since April 1, 2021, excluding the surcharge fee to the New Jersey Department of Community Affairs provided for in §
125-5 upon receipt of satisfactory proof of qualifications. This section providing for partial exemption from the U.C.C. fees for qualified religious, charitable and nonprofit organizations shall expire on December 31, 2023, unless further extended by formal action of the Township Council.
[Added 12-18-2018 by Ord.
No. 2018-22]
In addition to the fees specified above, a plan review fee pursuant
to N.J.A.C. 5:23-4.18 shall be computed as a percentage of the fee
to be charged for the construction permit. This percentage shall,
to the extent possible, approximate the actual costs incurred in plan
review activities, but in any case shall not be less than 5% nor more
than 25% of the amount that would be charged for the construction
permit.