No waivers or mitigation plans will be considered
for land disturbance activity that disturbs one acre or greater of
land.
All applicants are required to submit actual
"as-built" plans for any stormwater management practices located on-site
after final construction is completed. The plan must show the final
design specifications for all stormwater management facilities and
must be certified by a New York State licensed professional engineer.
A final inspection by the Town of Greece is required before the release
of any performance securities can occur.
All applicants are responsible for maintaining
the grading of the site so that it is consistent with the certified
"as-built" plans. Any postconstruction alterations to the landscape
shall receive prior approval from the Town of Greece. Temporary landscape
alterations, such as those associated with utility excavations and
landscaping activities, must be restored to conditions that are consistent
with the certified "as-built" plans.