Upon certification by the Zoning Officer of the completeness of an application for development pursuant to § 110-9A, the Board shall grant or deny approval within the number of days from the date of such certification as specified below or within such further time as may be consented to by the applicant. Failure of the Board to act within the time period for decision as prescribed below shall constitute approval of the application for development, and a certificate of the Zoning Officer as to the failure of the Board to act shall be issued on request of the applicant.
A.
Minor subdivisions applications: 45 days.
B.
Preliminary major subdivisions applications involving 10 lots or less: 45 days.
C.
Preliminary major subdivision applications involving more than 10 lots: 95 days.
D.
Final major subdivision applications: 45 days.
E.
Preliminary site plan applications involving 10 acres of land or less and 10 dwelling units or less: 45 days.
F.
Preliminary site plan applications involving more than 10 acres of land or more than 10 dwelling units: 95 days.
G.
Conditional use applications: 95 days.
H.
PURD applications: 95 days.
I.
Applications for variances or requests for issuance of a permit pursuant to N.J.S.A. 40:55D-34 or 40:55D-35: 120 days.
J.
Applications involving variances or requests for issuance of a permit, pursuant to N.J.S.A. 40:55D-34 or 40:55D-35, and also involving any type of site plan, subdivision and/or conditional use approval: 120 days. Should the applicant elect to submit a separate application for the variances or requests for issuance of a permit and a subsequent application requesting approval of the site plan, subdivision and/or conditional use, the one-hundred-twenty-day time period for decision shall apply only to the application for the variance or permit, and the time period for decision for the subsequent approval(s) shall be as otherwise provided in this section.