[Amended 6-8-2005 by L.L. No. 2-2005]
The applicant for the building sewer permit shall notify the Highland Sewer District Administrator or Town Engineer when the building sewer is ready for inspection and connection to the public sewer lateral. The connection shall be made under the supervision of the Highland Sewer District Administrator, or Engineer or his agent, or such other person as appointed by the Town Board. The applicant shall pay only the fee set forth in §
85-15C for the first inspection; however, if further inspections are necessary, there will be a fee of $50 for the second inspection, $100 for the third inspection, and $500 for the fourth inspection, and any subsequent inspections, such fees to be paid per request and inspection and are not cumulative.