Type of Service
|
Fee
| |||
---|---|---|---|---|
Building subcode fees
| ||||
Minimum fee
| ||||
R3/R5
|
$80
| |||
All other uses and commercial
|
$115
| |||
New construction, including additions, per cubic foot of volume
|
$0.053
| |||
Minimum fee for any new principal structure (R5)
|
$1,200
| |||
Minimum fee for any new accessory structure (R5)
|
$150
| |||
Minimum fee for additions (R5)
| ||||
120 square feet or less
|
$285
| |||
Greater than 120 square feet
|
$385
| |||
Modular structure, per $1,000 of cost
|
$30
| |||
Renovations, alterations and repairs
| ||||
Up to first $50,000 in cost, per $1,000
|
$30
| |||
From $50,001 to $100,000 and over in cost, per $1,000
|
$28
| |||
$100,001 and over in cost, per $1,000
|
$27
| |||
Demolitions
| ||||
R5 Use Group, complete
|
$300
| |||
All other use groups, complete
|
$700
| |||
Interior demolition, all use groups
|
$150
| |||
Garage or accessory building demolition, all use groups
|
$250
| |||
Fuel storage tanks, removal or abandon
| ||||
Up to 275 gallons
|
$75
| |||
276 to 1,000 gallons
|
$125
| |||
Each additional 500 gallons
|
$50
| |||
Moving a building, per $1,000 of estimated cost of work
|
$25
| |||
Asbestos abatement with administrative certificate
|
$175
| |||
Lead hazard abatement with certificate of clearance
|
$195
| |||
Swimming pools: building permit only
| ||||
Aboveground pools
|
$150
| |||
In-ground pools, per $1,000 of estimated cost
|
$30
| |||
Sheds, per $1,000 of estimated cost
|
$30
| |||
House and construction trailers, each
|
$150
| |||
Tents over 900 square feet or 30 feet in length in 1 direction
|
$150
| |||
Retaining walls 4 feet or more in height, per $1,000 of estimated
cost
|
$30
| |||
Signs, per square foot
|
$7
| |||
Certificate of occupancy, U.C.C.
| ||||
Residential (new construction or rehabilitation)
|
$100
| |||
Nonresidential
|
10% of permit fee
| |||
Certificate of continued occupancy, U.C.C., applicant-requested
| ||||
General visual inspection by all subcode officials, per subcode
|
$100
| |||
Temporary certificate of occupancy
| ||||
Initial issuance
|
No fee
| |||
Subsequent renewals, each
|
$30
| |||
Plan review (nonrefundable percentage of permit fee)
|
20%
| |||
Change of contractor (plus any additional items or cost)
|
$45
| |||
Withdrawn permit (administrative fee: percentage of permit fee)
|
30%
| |||
Reinstatement of lapsed permit fee (percentage of original permit
fee)
|
80%
| |||
Permit surcharge
|
State-mandated; see N.J.A.C. 5:23-4.19(b)
| |||
Variation application as per N.J.A.C. 5:23-2.10
| ||||
Class I structures
|
$550
| |||
Class II and Class III structures
|
$200
| |||
Resubmission, Class I structures
|
$200
| |||
Resubmission, Class II and Class III structures
|
$100
| |||
Special inspection request for a required code inspection, either
before or after regular Building Department hours of business or on
holidays and weekends
|
The current contractual hourly compensation rate (1 1/2
times their normal hourly salary) based on the amount of time required
for said inspection, with a 2-hour minimum, in addition to any established
permit and certificate fees
| |||
Electrical subcode fees
| ||||
Minimum fee
| ||||
R3/R5
|
$80
| |||
All other uses and commercial
|
$115
| |||
Electrical devices (lighting outlets, receptacles, switches,
smoke and heat detectors, emergency lights, exit lights, communication
points and fire alarm devices)
| ||||
1 to 20 devices
|
$80
| |||
Each additional 20 devices
|
$45
| |||
Dishwasher, disposal unit, instant hot, each
|
$50
| |||
Temporary trailers, each (plus the service)
|
$60
| |||
Motors (all except those in plug-in appliances)
| ||||
1 to 10 horsepower
|
$58
| |||
11 to 50 horsepower
|
$100
| |||
51 to 100 horsepower
|
$175
| |||
Greater than 100 horsepower
|
$450
| |||
Transformers/generators/appliance equipment/ovens, ranges, warming
trays
| ||||
1 to 10 kilowatts
|
$55
| |||
11 to 45 kilowatts
|
$80
| |||
46 to 112.5 kilowatts
|
$120
| |||
Over 112.5 kilowatts
|
$470
| |||
Service entrance, panel, subpanel or disconnect (each)
| ||||
Up to 100 amps
|
$100
| |||
101 to 200 amps
|
$120
| |||
201 to 400 amps
|
$220
| |||
401 to 1,200 amps
|
$560
| |||
Over 1,201 amps
|
$810
| |||
Additional meters included in service
|
$35
| |||
Air-conditioning units (includes disconnect, compressor/condenser,
air handler), each
|
$100
| |||
Replacement of any system part
|
$65
| |||
Burglar alarm system (complete)
|
$75
| |||
Swimming pools (includes receptacle, switch, trench, bonding
and equippotential bonding mat)
|
$190
| |||
Hydromassage tub (interior)
|
$60
| |||
Hot tub/spa, exterior (same as a pool)
|
$190
| |||
Certificate of compliance; annual inspection for public swimming
pools, spas and hot tubs
|
$135
| |||
Photovoltaic systems
| ||||
Solar modules
| ||||
1 to 20 modules
|
$85
| |||
Each additional 20 modules
|
$45
| |||
1 to 10 kilowatts
|
$80
| |||
11 to 100 kilowatts
|
$135
| |||
Greater than 100 kilowatts
|
$600
| |||
Disconnects and inverters
| ||||
Up to 100 amps, each
|
$95
| |||
101 to 200 amps, each
|
$115
| |||
EV Charging Station (Each)
|
$75
| |||
Elevator subcode fees
|
80% of state fees (subject to change by the state pursuant to
N.J.A.C. 5:23-12.6), plus 25% administrative fee
| |||
Elevator plan review
|
In accordance with N.J.A.C. 5:23-4.20(c)6 and 7
| |||
Fire subcode fees
| ||||
Minimum fee
| ||||
R3/R5
|
$80
| |||
All other uses and commercial
|
$115
| |||
Photovoltaic systems
| ||||
R3/R5
|
$80
| |||
All other uses commercial
|
$115
| |||
Sprinkler systems, each
| ||||
Pipe schedule
|
$90
| |||
Hydraulically calculated
|
$90
| |||
R5 Use Group, 20 or fewer heads
|
$80
| |||
Sprinkler system heads, all use groups
| ||||
1 to 20 heads
|
$90
| |||
21 to 100 heads
|
$160
| |||
101 to 200 heads
|
$297
| |||
201 to 400 heads
|
$760
| |||
401 to 1,000 heads
|
$1,060
| |||
Over 1,000 heads
|
$1,940
| |||
Sprinkler system supervisory devices (i.e., tamper switches
low/high), each
|
$35
| |||
Standpipes, each
|
$350
| |||
Dry pipe/alarm valves, each
|
$85
| |||
Preaction valves, each
|
$165
| |||
Water service for a fire line
|
$150
| |||
Fire alarm systems
| ||||
Control panels, R5 Use Group, each
|
$80
| |||
Control panels, all other use groups, each
|
$100
| |||
Fire alarm system devices (i.e., smoke detector heads, heat
detector heads, pull stations, water flow alarms)
| ||||
1 to 20 devices
|
$80
| |||
21 to 100 devices
|
$140
| |||
101 to 200 devices
|
$300
| |||
201 to 400 devices
|
$650
| |||
401 to 1,000 devices
|
$850
| |||
Over 1,000 devices
|
$1,200
| |||
Fire alarm panel, new installation or replacement
|
$100
| |||
Fire alarm system security devices (i.e., door locks, electromagnetic
releases), each
|
$45
| |||
Fire alarm system signaling devices (i.e., horns, strobes, bells),
each
|
$15
| |||
Independent preengineered systems, each
| ||||
Wet chemical system
|
$225
| |||
All other systems
|
$200
| |||
Gas- or oil-fired appliances, each
| ||||
R5 Use Group
|
$80
| |||
All other use groups
|
$115
| |||
Fireplaces
|
$85
| |||
Metal chimney liner
| ||||
Residential
|
$85
| |||
Commercial
|
$120
| |||
Exhaust systems, each
| ||||
Commercial kitchen hood
|
$250
| |||
Smoke control system
|
$350
| |||
Incinerators or crematoriums, each
|
$375
| |||
Fuel storage tanks, installation, each
| ||||
Up to 275 gallons
|
$85
| |||
276 to 1,000 gallons
|
$110
| |||
1,001 gallons to 5,000 gallons
|
$260
| |||
Over 5,000 gallons
|
$525
| |||
Fuel storage tanks, removal or abandon
| ||||
Up to 275 gallons
|
$80
| |||
276 to 1,000 gallons
|
$135
| |||
Each additional 500 gallons
|
$50
| |||
Fire pump, each
|
$400
| |||
Water service for fire line
| ||||
Up to 2-inch
|
$100
| |||
2 1/2- to 5-inch
|
$200
| |||
6-inch or larger
|
$300
| |||
Plumbing subcode fees
| ||||
Minimum fee
| ||||
R3/R5
|
$80
| |||
All other uses and commercial
|
$115
| |||
Fixtures (i.e., lavatories, kitchen sinks, basins, urinals,
water closets, bathtubs, shower stalls, sill cocks, laundry tubs,
floor drains, drinking fountains, dishwashers, garbage disposals,
clothes washers and similar devices), each
|
$35
| |||
Stacks, each
|
$60
| |||
Special devices (i.e., grease traps, oil separators, refrigeration
units, utility service connections, backflow preventers, gas service
interceptors, and fuel oil piping), each
|
$85
| |||
Utilization equipment (i.e., steam boilers, hot-water boilers,
warm-air furnaces), each
| ||||
R5 Use Group
|
$85
| |||
All other use groups
|
$110
| |||
Air-conditioning units, each
| ||||
R5 Use Group
|
$85
| |||
All other use groups
|
$95
| |||
Water heaters, each
| ||||
R5 Use Group
|
$85
| |||
All other use groups
|
$115
| |||
Gas piping, each
| ||||
R5 Use Group
|
$80
| |||
All other use groups
|
$90
| |||
Vapor recovery systems, each
|
$100
| |||
Required annual reinspections (i.e., cross-connections, backflow
preventers)
|
$75
| |||
Medical gas piping, per outlet
|
$40
| |||
Septic tank removal
|
$110
| |||
Lawn irrigation system (per system)
|
$85
| |||
Annual testing of backflow preventers
| ||||
1 to 4 devices
|
$75 per device
| |||
5 or more devices
|
$60 per device
| |||
Zoning
| ||||
Zoning permit (includes review for use and/or development)
| ||||
Initial
|
$60
| |||
Amended application, each
|
$35
| |||
Sign applications
|
$100
| |||
Certificate for resale of residential and commercial property
| ||||
With 2 weeks' notice
|
$100
| |||
With less than 2 weeks' notice
|
$150
| |||
House resale reinspection
|
$50
| |||
Application fee for outdoor dining (before April 1)
|
$100
| |||
Application fee for outdoor dining (after April 1)
|
$250
| |||
Certificate of use (business)
|
$225
| |||
Lead paint, visual inspection per unit
|
$220
| |||
Lead safe certificate (process from a third party)
|
$50
| |||
Any letter from the Zoning Official for nonconformity, zone
clarification, or permitted uses in a particular zone
|
$100
| |||
Engineer's escrow, minimum to be posted when associated with
a building permit
|
$1,000
| |||
Mechanical subcode fees
for R-3 and R-5 Uses
| ||||
(A) Minimum fee
|
$85
| |||
(B) Mechanical plan review
|
$85
| |||
(C) Replacement
| ||||
Furnaces, boilers, AC and HVAC units
|
$85 per unit replaced
| |||
Rooftop HVAC units
|
$140 per unit replaced
| |||
(D) Installation of aboveground or underground fuel storage
tanks
| ||||
Up to 275 gallons
|
$85 per unit
| |||
276 to 1,000 gallons
|
$110 per unit
| |||
(E) Fuel oil or gas piping connections
|
$85 per unit
| |||
(F) New installations: fireplaces, solid-fuel stoves, boilers,
furnaces, AC, HVAC, generators, chimneys and chimney relinings
|
$85 per unit
| |||
(G) Each additional unit over the initial (Lines C. D. E, F
from above)
|
$45 per unit
| |||
(H) Duct systems
|
$85 per system
| |||
(I) Metal chimney liner
|
$85
| |||
(J) Water heater
|
$85
|