Prior to the granting of final approval of subdivisions, the developer shall have installed all improvements specified in § 195-64 or shall have furnished performance guarantees as specified in § 195-65 for the ultimate installation of those improvements. Improvements for residential uses shall conform to the Residential Site Improvements Standards (RSIS), N.J.A.C. 5:21-1.1 et seq. These standards shall be considered the minimum for all nonresidential uses, with modifications or additions as required by the Township Engineer and Board having jurisdiction over the applications or as modified elsewhere in this Part 2.
A.
Streets. All streets shall be paved from curbline to curbline.
B.
Street signs. Appropriate street signs shall be installed at all street intersections and shall be of a type specified by the Division of Engineering. Street signs shall be installed prior to the issuance of certificates of occupancy, and the cost of signs and installation of same shall be borne by the subdivider.
C.
Clear view at intersections.
(1)
No fence, structure, planting or shrubbery over 30 inches in height above the level of the pavement at the center of the street, opposite the point in question, shall be erected, planted or maintained on any corner lot, in any zone, within 25 feet of the intersection formed by the projection of the two street sidelines at the corner.
(2)
No fence, structure, planting or shrubbery shall be permitted within three feet of any street sideline, on any lot, in any zone. The branches of all trees and shrubs projecting beyond such street sideline must be trimmed at all times in order to insure unobstructed vision and clearance eight feet above the ground or sidewalk level.
D.
Topsoil protection. No topsoil shall be removed from the site or used as spoil unless permission is first obtained from the Township Engineer and the Planning Board. Topsoil moved during the course of construction shall be redistributed so as to provide at least four inches of cover to all areas of the subdivision and shall be stabilized by seeding or planting.
E.
Monuments. Monuments shall be of the size and shape required by N.J.S.A. 46:26B-3 and shall be placed in accordance with such statute.
F.
Catch basins. Catch basins shall be constructed as directed and located by the Township Engineer.
G.
Soil or earth moving. No change shall be made in the elevation or contour of any lot or site, except as approved by the Township Engineer and the Planning Board. All changes in elevation and contours approved by the Township Engineer and the Planning Board shall be shown on the preliminary and final plat and profiles.
H.
Fire hydrants. Fire hydrants shall be installed in locations approved by the Fire Department.
I.
Construction stakes and grades. All construction stakes and grades thereon shall be set by a licensed professional engineer or land surveyor in the employ of the subdivider, or his/her contractor, and a duplicate copy of the notes made therefrom shall be filed with the Township Engineer.
J.
Commencement of construction work. No construction work shall commence without the Township Engineer being properly notified. Such notice shall be given at least one week before the commencement of work.
K.
Debris. All stumps, litter, rubbish, brush, weeds, dead and dying trees, roots and debris shall be removed from the site to the satisfaction of the Township Engineer. None of the above shall be buried or covered.
L.
Construction standards and specifications. The construction standards and specifications of the Township, as now or hereafter adopted, shall govern the construction and installation of all of the above improvements. Failure of the subdivider or his/her contractor or agent to conform to such specifications shall be just cause for the suspension of the work being performed and all permits being revoked, and no person shall have the right to demand or claim damages from the Township, its officers, agents or servants by reason of such suspension or revocation.
M.
Inspection. No underground installation shall be covered until inspection has been made and is approved by the Division of Engineering.
N.
As-built improvement plans. The subdivider shall provide and file with the Township Engineer one complete set of as-built improvement plans and profiles showing actual construction as approved prior to the release of the performance guarantees.