[Ord. No. 74, 5-7-2008]
(a)
No building hereafter erected shall be used or occupied in whole or in part until a certificate of occupancy has been issued by the Commissioner.
(b)
No building hereafter enlarged, altered, repaired, or upon which work has been performed which required the issuance of a building permit shall be occupied or used for more than 30 days after the completion of the work unless a certificate of occupancy has been issued by the Commissioner.
(c)
No change shall be made in the occupancy of an existing building unless a certificate of occupancy authorizing the change has been issued by the Commissioner.