[Ord. 338, 12/21/2015]
(a) 
The Township, the Township Engineer or their designee shall have the right to inspect all phases of the installation of the permanent stormwater management facilities as deemed appropriate by the Township.
(b) 
During any stage of the work, if the Township, Township Engineer or their designee determines that the permanent stormwater management facilities are not being installed in accordance with the approved SWM site plan, the Township may revoke any existing building permits and issue a cease-and-desist order until a revised SWM site plan is submitted and approved except as directed by the Township or Conservation District, as specified in this chapter.
(c) 
A final inspection of all stormwater management facilities shall be conducted by the Township or its designee and to confirm compliance with the approved SWM site plan prior to the issuance of any occupancy permit.