When changes from the construction drawings and specifications
become necessary during construction, a revised plan shall be submitted
to the Township and written acceptance by the Township Engineer shall
be secured before the execution of such changes.
Adequate provisions for the satisfactory maintenance of all
streets shall be made before dedication to and acceptance for maintenance
by the Township.
The applicant shall agree to construct and/or install improvements
required by the chapter as listed below:
E. Sidewalks and pedestrian paths.
H. Water supply system with fire-protection capability.
I. Public sanitary sewer system.
J. Electric, telephone, cable TV and communication facilities.
O. All other improvements required as part of the plan approval.
Relative to connection to the public sewer system, developer
shall be responsible for paying impact fees which have been adopted
by the Board of Supervisors in accordance with Act 203.
All on-site sewage disposal systems shall comply with Chapters
71 and 73 of the Pennsylvania Sewage Facilities Act, Act 537, County Health Department regulations, and all Township
ordinances.
The dimensional location of the on-site sewage system, alternate
system location, and the well must be shown on the plan prior to the
issuance of a building permit. The locations shall comply with the
Department of Environmental Resources, County Health Department and
Township regulations.