[Ord. of 1-6-1969, § 8]
(a)
The Director of Public Works, or his designated agent, is empowered to inspect, or cause to have inspected, at any time, any or all work being performed under a permit issued under this article.
(b)
If, in the opinion of the inspector, the work being performed does not meet the specifications and conditions approved or required, the permittee shall correct such conditions, commencing work within 24 hours of notification to make such correction, unless a longer period of time is allowed by the Director.
(c)
Work that has been completed and from which equipment and material have been removed will be subject to the same conditions as those cited in Subsection (b) of this section. If the permittee fails to comply, the Director may cause such work to be done and the permittee shall be liable for the full expense of such work.