A.
For any proposed development not exempt under § 281-5, the owner shall submit phased stormwater management plans or waiver application to the enforcement authority for review and approval. At a minimum, plans shall be submitted for the sketch plan, preliminary and final stormwater management construction phases of project design. Each plan submittal shall include the minimum content specified in § 281-14 of this chapter and meet the requirements of the Stormwater Design Manual and Article III of this chapter.
B.
The enforcement authority shall perform a comprehensive review of the stormwater management plans for each phase of site design. Coordinated comments will be provided for each plan phase that reflects input from all appropriate agencies, including but not limited to the Soil Conservation District (SCD), Critical Area Commission, Technical Advisory Committee and the Planning Commission. All comments from the enforcement authority and other appropriate agencies shall be addressed and approval received at each phase of project design before subsequent submissions.
C.
Notification of approval or reasons for disapproval or modification shall be given to the owner. If a decision is not made within 90 days, the owner shall be informed of the status of the review process and the anticipated completion date. The stormwater management plan shall not be considered approved without the inclusion on the plan of the dated signature of the enforcement authority.
D.
For sites with minimal improvements, such that ESD to the MEP is clearly met based upon the sketch plan review, the Town Engineer has the discretion to delete the preliminary development phase and move directly to the final development phase. This determination will be made at the sketch site plan review phase.