[Amended 12-7-1994 by Ord. No. 106-1994; 3-27-1996 by Ord. No. 9-1996; 9-24-1997 by Ord. No. 54-1997; 12-29-2003 by Ord. No. 74-2003; 10-20-2010 by Ord. No. 73-2010; 4-6-2016 by Ord. No. 18-2016]
The basic construction permit fee shall be the sum of the parts computed on the basis of the volume of the structure or the cost of construction, the number of plumbing fixtures and stacks, the number of electrical fixtures and devices, plus any special fees in each case. The minimum fee for a basic construction permit shall be $65. In the case of partial releases or fast-tracking, the total volume-based fee for new buildings or additions, or cost-based fees for alterations, replacements, repairs, etc., shall be paid at the time of release of the first partial building permit.
A. New construction or additions. The fees for new construction or additions shall be based upon the volume of the structure, as computed in accordance with N.J.A.C. 5:23-2.28. The new construction fee shall be in the amount of $0.038 per cubic foot of volume for buildings and structures of all use groups and types of construction as defined in Chapters 3 and 4 of the building subcode.
(1) Temporary structures and all structures for which volume cannot be computed, such as swimming pools and open structural towers, shall be charged a fee of $150.
(2) No fee shall be required for premanufactured construction, assembly or components transported to the construction site. A fee shall be required for work performed at the site, including but not limited to foundation systems, structural installations and external utility connections.
B. Renovations, alterations and repairs.
(1) Fees for renovations, alterations, repairs and combinations thereof shall be based upon the following schedule:
(a) For costs up to $50,000, the fee shall be $34 per $1,000 of cost.
(b) From $50,001 to $100,000, the fee shall be $26 per $1,000 of cost.
(c) For costs over $100,000, the fee shall be $22 per $1,000 of cost.
(2) For the purpose of determining estimated cost, the applicant shall submit to the Construction Official cost data produced by the architect or engineer of record or by a recognized estimating firm or by the contractor. A bonafide contractors bid, if available, shall be submitted. The construction official shall make the final decision regarding estimated cost.
(3) Where any material or labor proposed for installation in the building or structure is furnished or provided at no cost, the prevailing rate or cost shall be included in the estimated cost.
(4) There shall be a flat fee of $65 for all roofing and siding work completed on structures in Use Groups R-3 and R-4.
C. There shall be an additional fee of $64 per hour for review of any amendment or change to a plan that has already been released.