The petitioner, at his or her own expense, shall provide (design,
construct, install) the improvements required by these Regulations.
All improvements shall meet Town standards and specifications as found
in the Town Specifications for Public and Private Improvements.
The required improvements shall not be considered to be completed
until the installation of the improvements has been approved and certified
by the Town Engineer and a final as-built map has been submitted indicating
the location of monuments marking all underground utilities as actually
installed. In addition, a two-year maintenance bond for all required
improvements shall be submitted prior to acceptance of all the improvements
by the Town Engineer and issuance of a Public and Private Improvement
Permit. A maintenance bond shall be in the amount of 25 percent of
the construction cost for each utility.