The definitions set forth in Article XI of the Zoning Ordinance[1] of the Borough of Greencastle and Article II of the Subdivision and Land Development Ordinance of the Borough of Greencastle[2] are incorporated herein by reference.
[1]
Editor's Note: See Ch. 205, Zoning.
[2]
Editor's Note: See Ch. 180, Subdivision and Land Development.
Unless specifically defined below, words and phrases used in this chapter shall be interpreted so as to give this chapter its most reasonable application.
As used in this chapter, the following terms shall have the meanings indicated:
BASE FLOOD
A flood which has a one-percent chance of being equaled or exceeded in any given year (also called the one-hundred-year flood").
BASE FLOOD ELEVATION (BFE)
The elevation shown on the Flood Insurance Rate Map (FIRM) for Zones AE, AH, A1-30 that indicates the water surface elevation resulting from a flood that has a one-percent-or-greater chance of being equaled or exceeded in any given year.
DEVELOPMENT
Any man-made change to improved or unimproved real estate, including but not limited to the construction, reconstruction, renovation, repair, expansion, or alteration of buildings or other structures; the placement of manufactured homes; streets, and other paving; utilities; filling, grading and excavation; mining; dredging; drilling operations; storage of equipment or materials; and the subdivision of land.
EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed before the effective date of the floodplain management regulations adopted by a community.
EXPANSION TO AN EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
The preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads).
FLOOD
A temporary inundation of normally dry land areas.
FLOOD INSURANCE RATE MAP (FIRM)
The official map on which the Federal Emergency Management Agency or Federal Insurance Administration has delineated both the areas of special flood hazards and the risk premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
The official report provided by the Federal Emergency Management Agency that includes flood profiles, the Flood Insurance Rate Map, the Flood Boundary and Floodway Map, and the water surface elevation of the base flood.
FLOODPLAIN AREA
A relatively flat or low land area which is subject to partial or complete inundation from an adjoining or nearby stream, river or watercourse; and/or any area subject to the unusual and rapid accumulation of surface waters from any source.
FLOODPROOFING
Any combination of structural and nonstructural additions, changes, or adjustments to structures which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures and their contents.
FLOODWAY
The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than one foot.
GRADE, HIGHEST ADJACENT
The highest natural elevation of the ground surface prior to construction next to the proposed walls of a structure.
HISTORIC STRUCTURE
Any structure that is:
A. 
Listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;
B. 
Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district;
C. 
Individually listed on a state inventory of historic places in states which have been approved by the Secretary of the Interior; or
D. 
Individually listed on a local inventory of historic places in communities with historic preservation that have been certified either:
(1) 
By an approved state program as determined by the Secretary of the Interior; or
(2) 
Directly by the Secretary of the Interior in states without approved programs.
LOWEST FLOOR
The lowest floor of the lowest fully enclosed area (including basement). An unfinished, flood-resistant, partially enclosed area, used solely for parking of vehicles, building access, and incidental storage, in an area other than a basement area is not considered the lowest floor of a building, provided that such space is not designed and built so that the structure is in violation of the applicable nonelevation design requirements of this chapter.
MANUFACTURED HOME
A structure, transportable in one or more sections, which is built on a permanent chassis, and is designed for use with or without a permanent foundation when attached to the required utilities. The term includes park trailers, travel trailers, recreational and other similar vehicles which are placed on a site for more than 180 consecutive days.
MANUFACTURED HOME PARK OR SUBDIVISION
A parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.
MINOR REPAIR
The replacement of existing work with equivalent materials for the purpose of its routine maintenance and upkeep, but not including the cutting away of any wall, partition or portion thereof, the removal or cutting of any structural beam or bearing support, or the removal or change of any required means of egress, or rearrangement of parts of a structure affecting the exit way requirements; nor shall minor repairs include addition to, alteration of, replacement or relocation of any standpipe, water supply, sewer, drainage, drain leader, gas, oil, waste, vent, or similar piping, electric wiring or mechanical or other work affecting public health or general safety.
NEW CONSTRUCTION
Structures for which the start of construction commenced on or after the date of Borough of Greencastle's initial FIRM September 10, 1976, and includes any subsequent improvements thereto.
NEW MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after the effective date of floodplain management regulations adopted by a community.
RECREATIONAL VEHICLE
A vehicle which is:
A. 
Built on a single chassis;
B. 
Not more than 400 square feet, measured at the largest horizontal projections;
C. 
Designed to be self-propelled or permanently towable by a light-duty truck;
D. 
Not designed for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
REGULATORY FLOOD ELEVATION
The base flood elevation (BFE) plus a freeboard safety factor of 1 1/2 feet. NOTE: The one-and-one-half-foot freeboard is an alternative to the basic NFIP elevation requirement. Municipalities are free to establish freeboard requirements based on existing conditions, historical data, etc.
SPECIAL FLOOD HAZARD AREA (SFHA)
An area in the floodplain subject to a one-percent-or-greater chance of flooding in any given year. It is shown on the FIRM as Zone A, AO, A1-A30, AE, A99, or, AH.
START OF CONSTRUCTION
Includes substantial improvement and other proposed new development and means the date the land use permit was issued, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days from the date of the permit. The actual start means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. Permanent construction does not include land preparation, such as clearing, grading, and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers, or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For a substantial improvement, the actual start of construction means the first, alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
SUBSTANTIAL DAMAGE
Damage from any cause sustained by a structure whereby the cost of restoring the structure to its before-damaged condition would equal or exceed 50% or more of the market value of the structure before the damage occurred.
SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds 50% of the market value of the structure before the start of construction of the improvement. This term includes structures which have incurred substantial damage (or repetitive loss when a repetitive-loss provision is used) regardless of the actual repair work performed. The term does not, however, include either:
A. 
Any project for improvement of a structure to correct existing violations of state or local health, sanitary, or safety code specifications which have been identified by the local code enforcement official and which are the minimum necessary to assure safe living conditions; or
B. 
Any alteration of an historic structure, provided that the alteration will not preclude the structure's continued designation as an historic structure.
UNIFORM CONSTRUCTION CODE (UCC)
The statewide building code adopted by the Pennsylvania General Assembly in 1999 applicable to new construction in all municipalities whether administered by the municipality, a third party or the Department of Labor and Industry. Applicable to residential and commercial buildings, the Code adopted the International Residential Code (IRC) and the International Building Code (IBC), by reference, as the construction standard applicable with the state floodplain construction. For coordination purposes, references to the above are made specifically to various sections of the IRC and the IBC.
VIOLATION
The failure of a structure or other development to be fully compliant with the community's floodplain management regulations. A structure or other development without the elevation certificate, other certifications, or other evidence of compliance required in 44 CFR § 60.3(b)(5), (c)(4), (c)(10), (d)(3), (e)(2), (e)(4), or (e)(5)[1] is presumed to be in violation until such time as that documentation is provided.
[1]
Editor's Note: See the Pennsylvania Flood Plain Management Act of 1978, 32 P.S. § 679.101 et seq.